Final | 4/22/2011 | 4/25/2011 | 4/25/2011 | P | PASS |
Daryl Spivey
|
|
|
Should be someone there, if not gimme a call. Thanks, Daryl. Phone #: ###-#### >> Inspection requested via web by Josh Johnson
|
PLM-Aging Inspection | 4/5/2011 | 4/5/2011 | 4/5/2011 | | PASS |
Daryl Spivey
|
|
|
wip
|
Plumbing Rough-in | 1/29/2011 | 2/2/2011 | 2/2/2011 | A | PASS |
Daryl Spivey
|
|
|
Basement rough in inspection-last one! Phone #: ###-#### >> Inspection requested via web by Josh Johnson
|
Plumbing Rough-in | 1/24/2011 | 1/24/2011 | 1/24/2011 | A | PASS |
Daryl Spivey
|
|
|
master bathroom on main floor is ready for inspection. Thanks. Phone #: ###-#### >> Inspection requested via web by Josh Johnson
|
Groundwork | 1/12/2011 | 1/13/2011 | 1/13/2011 | P | PASS |
Jim Johnson
|
|
|
This inspection is for the sewer line replacement underground of the future master bedroom and bathroom. New main clean out included. Thanks. Phone #: ###-#### >> Inspection requested via web by Josh Johnson
|
Plumbing Rough-in | 1/6/2011 | 1/10/2011 | 1/10/2011 | A | PART |
Daryl Spivey
|
|
|
First thing Monday would be great. This is roughin inspection for new upstairs main bathroom and laundry room. Thanks. Phone #: ###-#### >> Inspection requested via web by Josh Johnson ok for cover on north side bath...........ds
|
Groundwork | 1/5/2011 | 1/5/2011 | 1/5/2011 | P | PASS |
Daryl Spivey
|
|
|
|
Plumbing Rough-in | 1/5/2011 | 1/5/2011 | 1/5/2011 | P | CANC |
Daryl Spivey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Josh Johnson
|