Final | 6/21/2011 | 6/22/2011 | 6/22/2011 | P | PASS |
Bill VanDegrift
|
|
|
Ready for final.....thanks. Todd will be contact if needed....###-#### Phone #: ###-#### >> Inspection requested via web by Carol Hazen final ok
|
Card not on site to sign | 6/22/2011 | 6/22/2011 | 6/22/2011 | A | PASS |
Bill VanDegrift
|
|
|
Ready for final.....thanks. Todd will be contact if needed....###-#### Phone #: ###-#### >> Inspection requested via web by Carol Hazen
|
Plumbing Rough-in | 5/11/2011 | 5/12/2011 | 5/12/2011 | P | PASS |
Jim Johnson
|
|
|
Todd is onsite contact....ready for plumbing rough inspection....ch Phone #: ###-#### >> Inspection requested via web by Carol Hazen
|
Plumbing Rough-in | 4/29/2011 | 4/29/2011 | 4/29/2011 | A | PASS |
Jim Johnson
|
|
|
|
Groundwork | 4/28/2011 | 4/29/2011 | 4/29/2011 | A | PASS |
Jim Johnson
|
|
|
Todd will be onsite for inspection. Phone #: ###-#### >> Inspection requested via web by Carol Hazen
|