Final | 9/7/2012 | 9/7/2012 | 9/7/2012 | P | PASS |
Jim Johnson
|
|
|
if questions call Matt @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann
|
Final | 8/27/2012 | 8/28/2012 | 8/28/2012 | A | PART |
Jim Johnson
|
|
|
CALL Mark to meet you there ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann
|
PLM-Aging Inspection | 7/31/2012 | 7/31/2012 | 7/31/2012 | | PASS |
Jim Johnson
|
|
|
|
Plumbing Rough-in | 5/1/2012 | 5/2/2012 | 5/2/2012 | P | PART |
Bill VanDegrift
|
|
|
if questions call Matt @ ###-####. Phone #: ###-#### >> Inspection requested via web by Stacia Haumann one sink east end of the building ok to cover
|
Water and/or Sewer | 4/18/2012 | 4/18/2012 | 4/18/2012 | P | PASS |
Jim Johnson
|
|
|
LATE PM. If questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann 4 inch sewer line on north side of building test ok ok to cover
|
Plumbing Rough-in | 4/12/2012 | 4/13/2012 | 4/13/2012 | A | PASS |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann rough-in marked on plan,s test ok ok to cover
|
Plumbing Rough-in | 4/3/2012 | 4/4/2012 | 4/4/2012 | A | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-####. Phone #: ###-#### >> Inspection requested via web by Stacia Haumann rough-in marked on plan,s test ok ok to cover
|
Groundwork | 3/28/2012 | 3/29/2012 | 3/29/2012 | A | CANC |
Daryl Spivey
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann Mark called and xld.......ds
|
Plumbing Rough-in | 2/29/2012 | 3/1/2012 | 3/1/2012 | A | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann
|
Plumbing Rough-in | 2/22/2012 | 2/23/2012 | 2/23/2012 | A | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann roof and overflow drain,s over mechanical room area test ok
|
Plumbing Rough-in | 2/20/2012 | 2/21/2012 | 2/21/2012 | A | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann roof and overflow drain,s marked on plans test ok
|
Groundwork | 2/9/2012 | 2/10/2012 | 2/10/2012 | A | PART |
Jim Johnson
|
|
|
water service stub in on south-east corner of building test ok ok to cover
|
Groundwork | 2/9/2012 | 2/9/2012 | 2/9/2012 | P | CANC |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann canc by Mark
|
Plumbing Rough-in | 2/7/2012 | 2/7/2012 | 2/7/2012 | P | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-####. Phone #: ###-#### >> Inspection requested via web by Stacia Haumann in wall water rough-in on restroom on south-west side of building test ok
|
Plumbing Rough-in | 2/3/2012 | 2/6/2012 | 2/6/2012 | P | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann roof drain,s and restroom,s on west side test ok marked on plan,s
|
Plumbing Rough-in | 1/12/2012 | 1/12/2012 | 1/12/2012 | P | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-####. Phone #: ###-#### >> Inspecti on requested via web by Stacia Haumann rough-in marked on plans ok ok to cover
|
Plumbing Rough-in | 1/9/2012 | 1/9/2012 | 1/9/2012 | P | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann
|
Groundwork | 1/9/2012 | 1/9/2012 | 1/9/2012 | P | PASS |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann groundwork marked on plan ok ok to cover
|
Plumbing Rough-in | 12/20/2011 | 12/21/2011 | 12/21/2011 | A | PART |
Jim Johnson
|
|
|
if questions call Kenny @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann portion of rough-in marked on plans test ok ok to cover
|
Groundwork | 11/23/2011 | 11/28/2011 | 11/28/2011 | A | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann ground work marked on plans test ok ok to cover
|
Plumbing Rough-in | 11/22/2011 | 11/23/2011 | 11/23/2011 | A | PART |
Jim Johnson
|
|
|
If questions call Mark @ ###-####. Phone #: ###-#### >> Inspection requested via web by Stacia Haumann rogh-in on D W V and water marked on plans test ok
|
Groundwork | 11/16/2011 | 11/17/2011 | 11/17/2011 | A | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann ground work marked on plan test ok ok to cover
|
Groundwork | 11/9/2011 | 11/10/2011 | 11/10/2011 | A | PART |
Jim Johnson
|
|
|
mark - ###-#### groundwork marked on plan,s test ok
|
Groundwork | 11/7/2011 | 11/7/2011 | 11/7/2011 | P | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann roof drains marked on plan test ok
|
Groundwork | 10/25/2011 | 10/25/2011 | 10/25/2011 | P | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann groundwork for water closet and two laves test ok marked on plans ok to cover
|
Other | 10/24/2011 | 10/24/2011 | 10/25/2011 | P | PART |
Jim Johnson
|
|
|
call bill conf. only
|
Other | 10/24/2011 | 10/25/2011 | 10/25/2011 | A | CANC |
Bill VanDegrift
|
|
|
call mark went over sewer loading, engineer will provide letter about grade, loading and existing sewer being 4" instead of the 6" shown on the plans.
|
Groundwork | 10/24/2011 | 10/24/2011 | 10/24/2011 | P | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann groundwork on 3 inch storm drain on north-west side test ok
|
Groundwork | 10/6/2011 | 10/7/2011 | 10/7/2011 | A | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann ground work in kit area test ok and rough-in on D W V ON TWO SINS TEST OK
|
Plumbing Rough-in | 10/3/2011 | 10/4/2011 | 10/4/2011 | A | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann water piping to existing restroom,s in middle of building test ok D W V piping to mec-room in mezzanine test ok portion of underground piping to new laundry area test ok
|
Other | 9/28/2011 | 9/28/2011 | 9/28/2011 | P | PART |
Jim Johnson
|
|
|
conf. and walk through with Bill Vandgrift and plumbing contractor
|
Other | 9/28/2011 | 9/28/2011 | 9/28/2011 | P | PART |
Bill VanDegrift
|
|
|
need to find original plan review from 2010
|
Groundwork | 9/20/2011 | 9/21/2011 | 9/21/2011 | P | PART |
Jim Johnson
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann main floor west end restroom,s ground work test ok
|