Final | 5/2/2012 | 5/2/2012 | 5/2/2012 | P | PASS |
Daryl Spivey
|
|
|
Jim i will have this ready at 1 P.m. thanks. Phone #: ###-#### >> Inspection requested via web by Brian Watson
|
Plumbing Rough-in | 3/13/2012 | 3/13/2012 | 3/13/2012 | P | PART |
Jim Johnson
|
|
|
Would like at 3 -- Brian Phone #: ###-#### D W V test ok in wall water rough-in test ok
|
Groundwork | 2/17/2012 | 2/17/2012 | 2/17/2012 | P | PASS |
Jim Johnson
|
|
|
request 1pm//###-#### Brian
|
Groundwork | 2/15/2012 | 2/16/2012 | 2/16/2012 | P | PART |
Jim Johnson
|
|
|
Jim, I should have this ready about 2:00. Thanks. Phone #: ###-#### >> Inspection requested via web by Brian Watson ground work on grease system test on still need to finish sanitary side
|
Water and/or Sewer | 2/14/2012 | 2/14/2012 | 2/14/2012 | P | PART |
Jim Johnson
|
|
|
Jim, I will have this grease trap ready by 11:30, if you can stop by. Phone #: ###-#### >> Inspection requested via web by Brian Watson outside grease interceptor and piping to interceptor and sewer line test ok
|