Final | 6/8/2012 | 6/11/2012 | 6/11/2012 | A | PASS |
Daryl Spivey
|
|
|
Bryan Phone #: ###-####
|
PLM-Aging Inspection | 6/4/2012 | 6/4/2012 | 6/4/2012 | | PASS |
Jim Johnson
|
|
|
|
Plumbing Rough-in | 3/2/2012 | 3/5/2012 | 3/5/2012 | A | PASS |
Jim Johnson
|
|
|
bryan Phone #: ###-####
|
Plumbing Rough-in | 2/28/2012 | 2/29/2012 | 2/29/2012 | A | PART |
Jim Johnson
|
|
|
bryan Phone #: ###-#### need to correct venting on floor drain need to support abs and pex piping as per table 3-2 need to test D W V and water system need to protect all piping with nail plates
|