Final | 1/2/2013 | 1/2/2013 | 1/2/2013 | P | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Final | 12/19/2012 | 12/20/2012 | 12/20/2012 | A | PART |
Jim Johnson
|
|
|
walk through with plumbing contractor need signage on non potable water system contractor to recall when ready
|
Final | 12/18/2012 | 12/19/2012 | 12/19/2012 | A | PART |
Jim Johnson
|
|
|
|
Final | 12/18/2012 | 12/18/2012 | 12/18/2012 | P | CANC |
Bill VanDegrift
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker jim will inspect wednesday am
|
Final | 10/29/2012 | 10/30/2012 | 10/30/2012 | P | PART |
Jim Johnson
|
|
|
This will be ready for a partial inspection on bathrooms and break room sink. Phone #: ###-#### >> Inspection requested via web by Travis Baker oked temp
|
Other | 10/26/2012 | 10/29/2012 | 10/29/2012 | P | CANC |
Jim Johnson
|
|
|
Looking for Partial Final on Bathrooms and Break room Phone #: ###-#### >> Inspection requested via web by Travis Baker Inspection cancelled from web by: Travis Baker
|
Plumbing Rough-in | 8/21/2012 | 8/21/2012 | 8/21/2012 | P | PART |
Jim Johnson
|
|
|
Bathroom rough-in is ready Any concerns call Travis ###-#### >> Inspection requested via web by Travis Baker restroom rough-in test ok ok to cover
|
Plumbing Rough-in | 8/6/2012 | 8/6/2012 | 8/6/2012 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker rough-in for break room area test ok ok to cover
|
Plumbing Rough-in | 7/9/2012 | 7/9/2012 | 7/9/2012 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker rough-in on new sink test ok
|
Groundwork | 6/27/2012 | 6/28/2012 | 6/28/2012 | A | PASS |
Jim Johnson
|
|
|
bathroom ground work on test Phone #: ###-#### >> Inspection requested via web by Travis Baker new restroom ground work test ok
|
Final | 6/13/2012 | 6/14/2012 | 6/14/2012 | P | CANC |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker Inspection cancelled from web by: Travis Baker
|
Groundwork | 5/17/2012 | 5/18/2012 | 5/18/2012 | A | PASS |
Jim Johnson
|
|
|
Travis Phone #: ###-####
|
Plumbing Rough-in | 5/11/2012 | 5/11/2012 | 5/11/2012 | P | PART |
Jim Johnson
|
|
|
Travis Phone #: ###-#### in wall rough-in only by trench drair test ok
|
Plumbing Rough-in | 5/7/2012 | 5/7/2012 | 5/7/2012 | P | PASS |
Daryl Spivey
|
|
|
Travis Phone #: ###-####
|
Groundwork | 4/26/2012 | 4/27/2012 | 4/27/2012 | A | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Groundwork | 4/11/2012 | 4/12/2012 | 4/12/2012 | A | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Water and/or Sewer | 3/28/2012 | 3/30/2012 | 3/30/2012 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker sewer line test ok an additional cleanout need in horizontal change in direction exceeding 135 degrees contractor to call when ready
|
Water and/or Sewer | 3/28/2012 | 3/29/2012 | 3/28/2012 | A | CANC |
Daryl Spivey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker Inspection cancelled from web by: Travis Baker
|
Groundwork | 3/8/2012 | 3/8/2012 | 3/8/2012 | P | PART |
Jim Johnson
|
|
|
groundwork on west side of building test ok
|
Water and/or Sewer | 3/5/2012 | 3/8/2012 | 3/8/2012 | A | NR |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker not ready
|