Sprinkler (Final) | 7/18/2012 | 7/18/2012 | 7/18/2012 | P | PASS |
Jim Johnson
|
|
|
|
Water and/or Sewer | 7/12/2012 | 7/16/2012 | 7/16/2012 | A | FAIL |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Peggy Pulley as per table 6-2 U PC 2003 installation of R.P. requires one (1) foot clearance at bottom of backflow device above finish grade for maintenance need to raise device one foot above finish grade. note- tie-in of controle valves ok ok to cover correction notice on site called contractor left message to call correction notice on site
|
Water and/or Sewer | 7/12/2012 | 7/12/2012 | 7/12/2012 | P | CANC |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Peggy Pulley Inspection cancelled from web by: Peggy Pulley
|