Final | 4/18/2013 | 4/19/2013 | 4/19/2013 | A | PASS |
Jim Johnson
|
|
|
Thank You Phone #: ###-#### >> Inspection requested via web by lon holtzmaster
|
Final | 4/17/2013 | 4/18/2013 | 4/18/2013 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by lon holtzmaster made walk through with plumbing contractor need to finish trim as per conversation on site oked temp contractor to recall when ready
|
Final | 4/15/2013 | 4/16/2013 | 4/16/2013 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by lon holtzmaster walk through with plumbing contractor for backflow,s on equipment
|
Final | 4/14/2013 | 4/15/2013 | 4/15/2013 | P | CANC |
Jim Johnson
|
|
|
Consulation / Partial final inspection Phone #: ###-#### >> Inspection requested via web by lon holtzmaster canc by contractor will recall when ready
|
Plumbing Rough-in | 3/4/2013 | 3/5/2013 | 3/5/2013 | P | PART |
Jim Johnson
|
|
|
2nd part of rough-in, Thanks Phone #: ###-#### >> Inspection requested via web by lon holtzmaster in wall rough-in ok ok to cover
|
Plumbing Rough-in | 2/28/2013 | 3/1/2013 | 3/1/2013 | A | PART |
Jim Johnson
|
|
|
Call Please so I can meet you there, Jim. Phone #: ###-#### >> Inspection requested via web by lon holtzmaster need to finish rough-in on storm drains need to retest D W V for women rest room need to test overflow drains finish nail plating
|
Final | 1/14/2013 | 1/15/2013 | 1/15/2013 | A | CANC |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by lon holtzmaster canc by contractor
|
Groundwork | 12/17/2012 | 12/17/2012 | 12/17/2012 | A | PASS |
Jim Johnson
|
|
|
|
Water and/or Sewer | 12/14/2012 | 12/17/2012 | 12/17/2012 | A | CANC |
Jim Johnson
|
|
|
lon Phone #: ###-####
|