Final | 11/7/2013 | 11/8/2013 | 11/8/2013 | P | PASS |
Jim Johnson
|
|
|
This is a final on the SHELL ONLY. Not a final on the entire permit. Phone #: ###-#### >> Inspection requested via web by Travis Baker note- no sign off card on site
|
Plumbing Rough-in | 10/18/2013 | 10/18/2013 | 10/18/2013 | P | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Plumbing Rough-in | 10/14/2013 | 10/15/2013 | 10/15/2013 | A | PASS |
Jim Johnson
|
|
|
Travis Phone #: ###-#### south side of building rough-in test ok
|
Groundwork | 7/3/2013 | 7/3/2013 | 7/3/2013 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker three inch under ground roof drain from mechanical room to west side of building test ok ok to cover
|
Groundwork | 6/28/2013 | 6/28/2013 | 6/28/2013 | A | PASS |
Jim Johnson
|
|
|
|
Groundwork | 6/26/2013 | 6/27/2013 | 6/27/2013 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker test ball leaking at building drain and building sewer connection need to correct test ball and retest contractor to recall when ready called contractor
|