Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberPLM13-02114
StatusFinaled
Name MAGIC PLUMBING
Site Address 2750 S PALMATIER WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
Plumbing Permit - New: Rough and trim plumbing of pool house
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final1/9/20141/9/20141/9/2014PPASS
DetailsBill VanDegrift
Phone #: ###-#### >> Inspection requested via web by Erin Whiting final ok
Card not on site to sign1/9/20141/9/20141/9/2014PPASS
DetailsBill VanDegrift
Phone #: ###-#### >> Inspection requested via web by Erin Whiting
Final12/11/201312/12/201312/12/2013PPEND
DetailsEric Strole
Phone #: ###-#### >> Inspection requested via web by Erin Whiting-All corrections complete except spout listings.
Final12/9/201312/10/201312/10/2013PFAIL
DetailsEric Strole
Phone #: ###-#### >> Inspection requested via web by Erin Whiting1-NEED TO CAULK DRINKING FOUNTAIN. 2-NEED TO TEST WATER HEATER FLUE. 3-NEED THE LISTING'S FOR FAUCETS AND SPOUTS.4-NEED LISTING FOR ANTIFREEZE USED FOR WATERLINES. 5-NEED TO CAP OFF WATERLINE BEFORE DBCA.
Final11/25/201311/25/201311/26/2013PFAIL
DetailsEric Strole
Phone #: ###-#### >> Inspection requested via web by Erin Whiting-1-NEED LISTINGS FOR LAV FCTS AND SPOUTS. 2-NEED LISTINGS FOR SHOWER VALVES. 3-NEED A WAY TO BLOW OUT WATERLINES FOR WINTER. 4-NEED TEMPERED WATER OFF 120 DEGREE OR LESS TO LAVS AND SHOWERS (CANNOT USE WATER HEATER). 5-NEED TO CAP OFF WATERLINE DOWNSTREAM OF BACKFLOWS OR ADD ANOTHER BACKFLOW. 6-NEED TO INSTALL DRINKING FOUNTAIN. 7-NEED TO INSTALL 2 OUTSIDE SHOWER VALVES. 8-BACKFLOWS NEED TESTWD AND CERTIFIED. 9-NEED TO TEST WATER HEATER FLUE 10-NEED COMBUSTION AIR FOR WATER HEATER. 11-NEED LETTER FROM OWNER TAKING RESPONSIBILITY FOR WINTERIZATION.
Plumbing Rough-in11/7/201311/7/201311/8/2013PPASS
DetailsEric Strole
Phone #: ###-#### >> Inspection requested via web by Erin Whiting
Water and/or Sewer10/31/201311/1/201311/1/2013ACANC
DetailsBill VanDegrift
Plumbing Rough-in10/31/201311/1/201311/1/2013ACANC
DetailsBill VanDegrift
Plumbing Rough-in10/31/201311/1/201311/1/2013APASS
DetailsBill VanDegrift
ok to pour walls inside both sides
Plumbing Rough-in10/30/201310/31/201310/31/2013ANR
DetailsEric Strole
Partial rough in insection Phone #: ###-#### >> Inspection requested via web by Erin Whiting
Plumbing Rough-in10/30/201310/30/201310/30/2013PFAIL
DetailsEric Strole
Phone #: ###-#### >> Inspection requested via web by Erin Whiting-No pex joints aloud in concrete
Groundwork9/30/20139/30/20139/30/2013PPASS
DetailsEric Strole
>> Inspection requested via web by Erin Whiting-g/w pass. still need sewer hook-up.
Plumbing Rough-in9/9/20139/10/20139/10/2013APART
DetailsEric Strole
partial rough-in for dwv in concrete walls. Still need sewer hook-up and the rest of the ground work and rough-in.
Plumbing Rough-in9/6/20139/9/20139/9/2013PCANC
DetailsEric Strole
Phone #: ###-#### >> Inspection requested via web by Erin Whiting
Groundwork8/8/20138/8/20138/8/2013APASS
DetailsDaryl Spivey
Plumbing Rough-in8/7/20138/8/20138/8/2013ACANC
DetailsDaryl Spivey
Phone #: ###-#### >> Inspection requested via web by Erin Whiting