Final | 3/19/2014 | 3/20/2014 | 3/20/2014 | A | PASS |
Daryl Spivey
|
|
|
Backflow devices are getting tested Thursday morning Thanks Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Plumbing Rough-in | 1/31/2014 | 1/31/2014 | 1/31/2014 | P | PASS |
Daryl Spivey
|
|
|
Could you make this your last inspection of the day? Thanks Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Groundwork | 12/31/2013 | 12/31/2013 | 12/31/2013 | P | PASS |
Daryl Spivey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Groundwork | 12/30/2013 | 12/30/2013 | 12/30/2013 | P | FAIL |
Daryl Spivey
|
|
|
We had to relocate main water line inside of building Phone #: ###-#### >> Inspection requested via web by Travis Baker copper water needs to be brazed under concrete floor..............ds
|
Groundwork | 12/13/2013 | 12/13/2013 | 12/13/2013 | P | PASS |
Jim Johnson
|
|
|
Is it possible to get an inspection right after lunch we would like to backfill it today. Thanks Phone #: ###-#### >> Inspection requested via web by Travis Baker grease line piping test ok
|
Groundwork | 12/4/2013 | 12/5/2013 | 12/5/2013 | A | PART |
Daryl Spivey
|
|
|
Sanitary sewer only is ready for inspection Phone #: ###-#### >> Inspection requested via web by Travis Baker sanitary tested ok........ds
|