Final | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | PASS |
Daryl Spivey
|
|
|
call for key location // Sylvan Phone #: ###-####
|
Plumbing Rough-in | 5/1/2014 | 5/2/2014 | 5/2/2014 | P | PASS |
Eric Strole
|
|
|
Reinspect Phone #: ###-#### >> Inspection requested via web by Steve Spence
|
Plumbing Rough-in | 4/28/2014 | 4/29/2014 | 4/29/2014 | A | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Steve Spence-correction still not complete
|
Plumbing Rough-in | 4/24/2014 | 4/25/2014 | 4/25/2014 | A | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Steve Spence-Not enough vents thru roof to equal the cross sectional required.
|
Groundwork | 3/24/2014 | 3/25/2014 | 3/25/2014 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Steve Spence
|