Final | 7/22/2014 | 7/22/2014 | 7/22/2014 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by MICHAEL BYERS-No sign off card posted
|
Plumbing Rough-in | 5/29/2014 | 5/30/2014 | 5/30/2014 | A | PASS |
Eric Strole
|
|
|
just wanted you to see that we fixed the back graded vent and added a hanger on the vents above the bathroom Phone #: ###-#### >> Inspection requested via web by MICHAEL BYERS
|
Plumbing Rough-in | 5/12/2014 | 5/12/2014 | 5/12/2014 | P | PART |
Eric Strole
|
|
|
plumbing rough in of 2 bathrooms. Please let me know if there will be anything else needed that is needed beyond adding premise protection for the domestic water, so I can present it to the general now so they are not waiting on getting a final when it gets to that point Thank you Phone #: ###-#### >> Inspection requested via web by MICHAEL BYERS-Ok to cover walls, need to fix reverse grade on overhead vent back bath and add hanger on overhead vent front bath. By final need to install dbca on water service, need to isolate all hosebibs in mechanic shop with a rpba and labet non-potable do not drink per 2009 ISPC and need thermal expantion tank.
|
Groundwork | 4/29/2014 | 4/30/2014 | 4/30/2014 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by MICHAEL BYERS
|