Final | 11/12/2014 | 11/13/2014 | 11/13/2014 | A | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Groundwork | 10/15/2014 | 10/16/2014 | 10/16/2014 | A | PASS |
Bill VanDegrift
|
|
|
Tony Phone #: ###-#### water service test ok
|
Plumbing Rough-in | 10/3/2014 | 10/3/2014 | 10/3/2014 | A | PASS |
Jim Johnson
|
|
|
Provisions have been made to prevent pipes from freezing Phone #: ###-#### >> Inspection requested via web by Travis Baker
|
Plumbing Rough-in | 9/26/2014 | 9/26/2014 | 9/26/2014 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker need to repipe water lines in argo room 101 where wall and soffit meet due to freezing condition,s contractor to recall when ready
|
Water and/or Sewer | 8/28/2014 | 8/28/2014 | 8/28/2014 | A | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Baker building sewer tie ok ok to cover
|
Groundwork | 7/30/2014 | 7/31/2014 | 7/31/2014 | A | PASS |
Bill VanDegrift
|
|
|
Phone #: ###-#### Inspection requested via web by Travis Baker gwok
|
Groundwork | 7/17/2014 | 7/18/2014 | 7/18/2014 | A | PART |
Jim Johnson
|
|
|
Groundwork partially complete. Need inspection so footers can be poured over plumbing. Phone #: ###-#### >> Inspection requested via web by Travis Baker north end of building dwv and south end of build ing trunk line for bathroom group dwv test ok contractor will finish dwv on bathroom group after footing are poured
|