Final | 3/31/2015 | 4/1/2015 | 4/1/2015 | A | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ryan Baker
|
Plumbing Rough-in | 2/23/2015 | 2/24/2015 | 2/24/2015 | A | PASS |
Jim Johnson
|
|
|
please call before heading over Phone #: ###-#### >> Inspection requested via web by Ryan Baker
|
Water and/or Sewer | 11/20/2014 | 11/21/2014 | 11/21/2014 | A | PASS |
Jim Johnson
|
|
|
Lou Phone #: ###-#### sewer line test ok ok to cover
|
Water and/or Sewer | 11/10/2014 | 11/10/2014 | 11/10/2014 | P | PART |
Jim Johnson
|
|
|
Just need the main water line that comes into the building to be inspected.. The water meter is on.. Thanks Phone #: ###-#### >> Inspection requested via web by Ryan Baker water line test ok need blue tracer wire installed told general contractor on site ok to cover after tracer wire is installed due to trench location for traffic area
|
Water and/or Sewer | 10/23/2014 | 10/24/2014 | 10/24/2014 | A | CANC |
Jim Johnson
|
|
|
Please call before heading over please Phone #: ###-#### >> Inspection requested via web by Ryan Baker this inspection is for a groundwork
|