Final | 2/12/2015 | 2/12/2015 | 2/12/2015 | P | PASS |
Jim Johnson
|
|
|
permit finaled for portion of ground work only
|
Water and/or Sewer | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | FAIL |
Jim Johnson
|
|
|
Jason// please call before Phone #: ###-#### need to protect pex piping passing through metal stud,s need nail plates where needed need to provide backing support for water heater and mop sink water outlets called Jason will recall when ready
|
Groundwork | 11/26/2014 | 11/26/2014 | 11/28/2014 | P | PART |
Jim Johnson
|
|
|
Please call 30 min prior for meet - Keith Phone #: ###-#### or Jason ###-#### groundwork for grease line test ok ok to cover
|
Plumbing Rough-in | 11/25/2014 | 11/25/2014 | 11/25/2014 | P | FAIL |
Jim Johnson
|
|
|
Keith-underground drain lines-please call 30 minutes prior Phone #: ###-#### need to repipe 3 inch building drain for grease line to 4 inch as per the approved plan or provide letter from mechanical ergineer saying 3inch will be ok for grease building drain to grease interceptor talked with contractor on site
|