Final | 5/26/2015 | 5/27/2015 | 5/27/2015 | A | PASS |
Jim Johnson
|
|
|
|
Final | 5/26/2015 | 5/26/2015 | 5/26/2015 | P | NR |
Jim Johnson
|
|
|
if questions call Matt @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann
|
Plumbing Rough-in | 2/18/2015 | 2/18/2015 | 2/18/2015 | P | PASS |
Jim Johnson
|
|
|
if questions call Matt @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann
|
Med/Gas Systems | 2/17/2015 | 2/17/2015 | 2/17/2015 | P | PART |
Jim Johnson
|
|
|
24 pressure test from operatory to zone valves test ok
|
Med/Gas Systems | 2/13/2015 | 2/13/2015 | 2/13/2015 | P | PART |
Jim Johnson
|
|
|
med gas pressure test. if questions please call Matt @ ###-####. Phone #: ###-#### >> Inspection requested via web by Stacia Haumann start of 24 hr pressure test on med gas from operatory room, to zone valve,s
|