Final | 9/18/2015 | 9/21/2015 | 9/21/2015 | A | PASS |
Jim Little
|
|
|
Phone #: ###-#### Inspection requested via web by Travis Baker
|
Final | 9/11/2015 | 9/11/2015 | 9/11/2015 | P | CANC |
Eric Strole
|
|
|
This is will be ready for a partial final. Phone #: ###-#### Inspection requested via web by Travis Baker
|
Plumbing Rough-in | 9/10/2015 | 9/10/2015 | 9/10/2015 | P | PART |
Bill VanDegrift
|
|
|
Call Travis to get details on where all the gauges are located Phone #: ###-#### Inspection requested via web by Travis Baker non-potable water piping test ok, needs labels. roof drain test ok, swamp cooler drains ok. move non-potable water connection to existing to downstream of premise dcva. provide secondary roof drainage. roof drain strainers required.
|
Plumbing Rough-in | 9/10/2015 | 9/10/2015 | 9/10/2015 | A | CANC |
Eric Strole
|
|
|
Call Travis to get details on where all the gauges are located Phone #: ###-#### Inspection requested via web by Travis Baker
|
Groundwork | 7/14/2015 | 7/15/2015 | 7/15/2015 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Travis Baker-8" roofdrain stub in and out of building ok to cover.
|
Groundwork | 7/13/2015 | 7/14/2015 | 7/14/2015 | P | NR |
Jim Little
|
|
|
Phone #: ###-#### Inspection requested via web by Travis Baker
|