Final | 5/12/2016 | 5/12/2016 | 5/12/2016 | A | PASS |
Jim Little
|
|
|
>med gas 3rd party received, final occ ok.
|
Final | 5/2/2016 | 5/3/2016 | 5/3/2016 | A | PART |
Jim Little
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige >final plumbing ok >need med gas cert
|
Med/Gas Systems | 4/29/2016 | 5/2/2016 | 5/2/2016 | A | PASS |
Jim Little
|
|
|
Med gas pressure test Phone #: ###-#### Inspection requested via web by Nicholas Paige >Vacuum test ok
|
Final | 4/27/2016 | 4/28/2016 | 4/28/2016 | A | NR |
Eric Strole
|
|
|
Med gas and plumbing finals Phone #: ###-#### Inspection requested via web by Nicholas Paige-Need to finish and test vac system. Need to test all backflows. Need 3rd party med gas cert papers.
|
Other | 2/12/2016 | 2/12/2016 | 2/12/2016 | P | NR |
Bill VanDegrift
|
|
|
will need to retest the dental gas system after valve boxs are changed out for the building inspector.
|
Med/Gas Systems | 2/10/2016 | 2/11/2016 | 2/11/2016 | A | CANC |
Jim Little
|
|
|
check approved plans after plan mod-as per Bill V. Will need another dental gas system test before bldg inspector can let them cover
|
Med/Gas Systems | 2/9/2016 | 2/10/2016 | 2/10/2016 | P | PART |
Jim Little
|
|
|
vac on 32# oxy on 170# N2 on 170# N2O on 170# >med gas test ok >resched for am to check approved plans
|
Med/Gas Systems | 2/8/2016 | 2/9/2016 | 2/9/2016 | P | PART |
Bill VanDegrift
|
|
|
please call jeremy with any questions Phone #: ###-#### Inspection requested via web bNicholas Paige start dental gas test I set up an inspection for tomorrow pm. The approved plans are back in the office for a plan mod, shouldnt effect system.
|
Plumbing Rough-in | 2/4/2016 | 2/4/2016 | 2/4/2016 | P | PASS |
Jim Little
|
|
|
please call Jeremy with any questions Phone #: ###-#### Inspection requested via web by Nicholas Paige >plumbing ri ok
|