Final | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | PASS |
Eric Strole
|
|
|
IF QUESTIONS CALL JERRY @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-Per Bill Vandegrift final ok.
|
Final | 4/28/2017 | 5/2/2017 | 5/2/2017 | A | PART |
Eric Strole
|
|
|
10 AM - If questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-Temp final ok
|
Final | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | PEND |
Eric Strole
|
|
|
If questions call Jerry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann-Need commissioning report.
|
Final | 4/5/2017 | 4/6/2017 | 4/6/2017 | A | PEND |
Eric Strole
|
|
|
If questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-Waiting on being able to give a temp final.
|
Groundwork | 3/15/2017 | 3/15/2017 | 3/15/2017 | P | PASS |
Eric Strole
|
|
|
Domestic water underground inspection. If questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-Waterline to outside drinking fountain installed and buried without any inspections. Test pass.
|
PLM-Aging Inspection | 3/7/2017 | 3/7/2017 | 3/7/2017 | | PART |
Eric Strole
|
|
|
wip
|
Plumbing Rough-in | 12/6/2016 | 12/6/2016 | 12/6/2016 | P | PASS |
Eric Strole
|
|
|
Rain Drain (R-I); if questions call Jerry Prough @ ####-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-Roof drain pass
|
Plumbing Rough-in | 10/7/2016 | 10/7/2016 | 10/7/2016 | P | PASS |
Daryl Spivey
|
|
|
if questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Plumbing Rough-in | 9/14/2016 | 9/14/2016 | 9/14/2016 | A | PART |
Eric Strole
|
|
|
Grid 1-4 pass
|
Other | 9/13/2016 | 9/13/2016 | 9/13/2016 | P | DONE |
Eric Strole
|
|
|
Conferance on material in open plenum.
|
Plumbing Rough-in | 9/12/2016 | 9/12/2016 | 9/12/2016 | P | FAIL |
Eric Strole
|
|
|
if questions call Jerry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann-Cannot have combustables in an open plenum.
|
PLM-Aging Inspection | 6/24/2016 | 6/24/2016 | 6/24/2016 | | PART |
Eric Strole
|
|
|
wip
|
Other | 3/21/2016 | 3/21/2016 | 3/21/2016 | P | PART |
Eric Strole
|
|
|
underground rain drains. If questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Groundwork | 3/14/2016 | 3/15/2016 | 3/15/2016 | A | PART |
Eric Strole
|
|
|
Underground Sanitary Waste, storm drain, Domestic Underground.
If questions call Jerry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann-Section complete is marked on plans.
|
Groundwork | 3/10/2016 | 3/11/2016 | 3/11/2016 | A | PART |
Eric Strole
|
|
|
Partial U/G waste piping. If questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-Section complete is marked on plans.
|
Groundwork | 1/18/2016 | 1/19/2016 | 1/19/2016 | A | PASS |
Eric Strole
|
|
|
DOMESTIC WATER UNDERGROUND. IF QUESTIONS CALL JERRY @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-Test on water service pass.
|