Final | 4/5/2016 | 4/5/2016 | 4/5/2016 | P | PASS |
Jim Little
|
|
|
Mait Phone #: ###-#### Inspection requested via web by j mait downer jr >
|
Plumbing Rough-in | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Jim Little
|
|
|
Radiant pipe inspection Phone #: ###-#### Inspection requested via web by j mait downer jr >snowmelt for slab ok
|
Groundwork | 3/3/2016 | 3/3/2016 | 3/3/2016 | P | PASS |
Jim Little
|
|
|
Trench drain...mait Phone #: ###-#### Inspection requested via web by j mait downer jr
|
Groundwork | 1/28/2016 | 1/28/2016 | 1/28/2016 | P | PASS |
Bill VanDegrift
|
|
|
gw reinspect
|
Groundwork | 1/28/2016 | 1/28/2016 | 1/28/2016 | A | FAIL |
Jim Little
|
|
|
gw for boiler room 1> increase one vent to 3" for CSA of venting 2> need a 10' head on test 3> use proper bands for cast iron to pvc transition.
|
Groundwork | 1/22/2016 | 1/22/2016 | 1/22/2016 | P | PART |
Jim Little
|
|
|
Part ground work Phone #: ###-#### Inspection requested via web by j mait downer jr >drain stubbed into new boiler room ok
|