Final | 6/22/2016 | 6/22/2016 | 6/22/2016 | A | PASS |
Jim Little
|
|
|
work complete
|
Water and/or Sewer | 3/30/2016 | 3/30/2016 | 3/30/2016 | A | PASS |
Jim Little
|
|
|
water line insp
|
Water and/or Sewer | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PART |
Jim Little
|
|
|
main water and connection insp. >ok to bury except at 90's
|
Water and/or Sewer | 3/24/2016 | 3/24/2016 | 3/24/2016 | P | PART |
Jim Little
|
|
|
main water >pvc female adp. to copper male adp. not an approved connection per 606.2.2 UPC >ok to bury except at building connection.
|
Water and/or Sewer | 3/22/2016 | 3/22/2016 | 3/22/2016 | P | NR |
Jim Little
|
|
|
water line inspection per Pete
|
Water and/or Sewer | 3/11/2016 | 3/11/2016 | 3/11/2016 | P | PASS |
Jim Little
|
|
|
Mark-sewer only Phone #: ###-#### ok to bury sewer from tanks
|
Water and/or Sewer | 3/10/2016 | 3/10/2016 | 3/10/2016 | P | PART |
Jim Little
|
|
|
check interceptors >interceptors test ok
|
Water and/or Sewer | 3/9/2016 | 3/9/2016 | 3/9/2016 | P | FAIL |
Jim Little
|
|
|
Mark-sewer only Phone #: ###-#### >swap cleanouts so all sections can be snaked >add 6" cleanout as per plan >start 24hr test on incpeptors
|
Water and/or Sewer | 3/3/2016 | 3/4/2016 | 3/4/2016 | A | PART |
Jim Little
|
|
|
Mark Phone #: ###-#### >4" ss to tanks ok from carwash and service >need to water test tanks
|
Storm Drains | 2/23/2016 | 2/24/2016 | 2/24/2016 | A | PART |
Jim Little
|
|
|
SD, se corner >s.e. corner sd from rd ok to bury
|
Storm Drains | 2/22/2016 | 2/23/2016 | 2/23/2016 | P | PART |
Jim Little
|
|
|
sd west side >west side storm drain,ok
|
Storm Drains | 2/22/2016 | 2/22/2016 | 2/22/2016 | P | PART |
Jim Little
|
|
|
north side SD >Sd east side and west of carwash side ok
|
Groundwork | 2/19/2016 | 2/22/2016 | 2/22/2016 | A | NR |
Jim Little
|
|
|
Phone #: ###-####
|
Storm Drains | 2/19/2016 | 2/19/2016 | 2/19/2016 | P | DONE |
Jim Little
|
|
|
partial SD inspection, Tom is onsite. >consult on work, need wyes instead of tee's
|