Final | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Tobi Wilson
|
Plumbing Rough-in | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | PASS |
Jim Little
|
|
|
Phone #: ###-#### Inspection requested via web by Tobi Wilson
|
Plumbing Rough-in | 3/29/2016 | 3/30/2016 | 3/30/2016 | A | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Tobi Wilson-Need to change softner drain to 1 1/2" and wet vent on tub vent. Need to tie upstairs fixtures into 3" stack.
|
Plumbing Rough-in | 3/28/2016 | 3/29/2016 | 3/29/2016 | A | FAIL |
Jim Little
|
|
|
key is on top of electric box Phone #: ###-#### Inspection requested via web by Tobi Wilson >Mst sh, lav and softener drain need to tie onto 3" stack instead of basement tub vent.. >basement lav, washerbox and sink need to tie into a drain instead of vent from floor drain.
|
Other | 3/14/2016 | 3/16/2016 | 3/16/2016 | A | FAIL |
Eric Strole
|
|
|
CONSULTATION INSPECTION Phone #: ###-#### Inspection requested via web by Tobi Wilson-Conferance on plumbing work being done without permit. Plumb per 2009 ISPC.
|