Final | 9/30/2016 | 10/4/2016 | 10/4/2016 | A | PASS |
Bill VanDegrift
|
|
|
David Phone #: ###-####
|
Final | 9/29/2016 | 9/30/2016 | 9/30/2016 | A | PART |
Bill VanDegrift
|
|
|
Myron Phone #: ###-#### needs rp at ice maker lowered to 60" max.
|
Final | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | PART |
Bill VanDegrift
|
|
|
Benjamin Phone #: ###-#### ice mechine will get an rp, test all backflow preventors. set all equipment.
|
Other | 9/1/2016 | 9/1/2016 | 9/1/2016 | P | PASS |
Eric Strole
|
|
|
20 lb gas test and rough-in pass
|
Med/Gas Systems | 8/29/2016 | 9/1/2016 | 9/1/2016 | A | FAIL |
Eric Strole
|
|
|
Ben Phone #: ###-####-20 lb gas test fail
|
Plumbing Rough-in | 8/26/2016 | 8/29/2016 | 8/29/2016 | A | FAIL |
Eric Strole
|
|
|
8:00 AM-20 lb gas test fail. 20 lb gas test requires no more then a 30 lb gauge. From last inspection need mission couplings on roof drains from cast iron to pvc.
|
Plumbing Rough-in | 8/25/2016 | 8/26/2016 | 8/26/2016 | P | PART |
Eric Strole
|
|
|
David Phone #: ###-####-Vent for interceptor is required to be 3" up thru roof and gas gauge will not zero out.
|
Groundwork | 7/21/2016 | 7/25/2016 | 7/25/2016 | P | PART |
Eric Strole
|
|
|
Ben Phone #: ###-####-3" water supply pass
|
Groundwork | 7/14/2016 | 7/14/2016 | 7/14/2016 | A | PEND |
Eric Strole
|
|
|
Underground - Benjamin Phone #: ###-####-Need to run waterline under slab per 609.2 or provide documentation per 301.2 of the 2009 ISPC. Copper pipe under is required to be at least type L copper per 604.2 of the 2009 ISPC. Need complete before rough-in inspection. Left correction notice on site.
|
Plumbing Rough-in | 7/13/2016 | 7/14/2016 | 7/14/2016 | A | CANC |
Eric Strole
|
|
|
Underground - Benjamin Phone #: ###-####-Changed to groungwork
|
Groundwork | 7/6/2016 | 7/7/2016 | 7/7/2016 | P | PART |
Eric Strole
|
|
|
Ben Phone #: ###-####-DWV pass. Waterline to be run at a later date.
|