Final | 6/30/2016 | 7/1/2016 | 7/1/2016 | P | PASS |
Bill VanDegrift
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER final ok
|
Plumbing Rough-in | 6/23/2016 | 6/24/2016 | 6/24/2016 | A | PASS |
Jim Little
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
Plumbing Rough-in | 6/23/2016 | 6/23/2016 | 6/23/2016 | P | FAIL |
Jim Little
|
|
|
re inspect >leak on dwv in restroom >still missing nail plates >still need to test foot vents in column's. ok to cover columns.
|
Plumbing Rough-in | 6/22/2016 | 6/23/2016 | 6/23/2016 | A | FAIL |
Jim Little
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER >add c/o's to all foot vents and test. >test dwv in restroom. >add missing nailplates.
|
Groundwork | 6/20/2016 | 6/20/2016 | 6/20/2016 | P | PASS |
Jim Little
|
|
|
>check remaining work
|
Groundwork | 6/14/2016 | 6/20/2016 | 6/20/2016 | A | PART |
Jim Little
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER >part gw is ok,
|