Final | 9/19/2016 | 9/20/2016 | 9/20/2016 | A | PASS |
Eric Strole
|
|
|
For access Call Ryan @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Final | 9/19/2016 | 9/19/2016 | 9/19/2016 | P | NH |
Eric Strole
|
|
|
For access Call Ryan @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-No access
|
Med/Gas Systems | 9/12/2016 | 9/13/2016 | 9/13/2016 | P | PASS |
Eric Strole
|
|
|
Test on med gas pass.
|
Med/Gas Systems | 9/12/2016 | 9/12/2016 | 9/12/2016 | P | PART |
Eric Strole
|
|
|
CALL 30 MINS PRIOR to arrival - Ryan ###-####. Witness test for Med Gas. Phone #: ###-#### Inspection requested via web by Stacia Haumann-Start of 24 hr test.
|
Med/Gas Systems | 8/22/2016 | 8/23/2016 | 8/23/2016 | A | PART |
Eric Strole
|
|
|
Test in room only pass.
|
Med/Gas Systems | 8/19/2016 | 8/22/2016 | 8/22/2016 | A | PART |
Eric Strole
|
|
|
med gas pressure test witness - if questions call Ryan @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann-Start of 24 hr test. Droped gauges to 60 lbs.
|
Plumbing Rough-in | 8/15/2016 | 8/16/2016 | 8/16/2016 | A | PART |
Eric Strole
|
|
|
RI inspection in the ceiling cover. any questions please call Ryan @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-Do not cover ceiling. Rough-in not complete.
|
Plumbing Rough-in | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Eric Strole
|
|
|
|
Groundwork | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Eric Strole
|
|
|
|
Plumbing Rough-in | 7/20/2016 | 7/20/2016 | 7/20/2016 | P | FAIL |
Eric Strole
|
|
|
Wall Rough-In - If questions call ryan @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann-Need approved plans on site.
|
Groundwork | 7/20/2016 | 7/20/2016 | 7/20/2016 | P | FAIL |
Eric Strole
|
|
|
if questions call ryan @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann-Need approved plans on site.
|