Final | 8/11/2016 | 8/12/2016 | 8/12/2016 | A | PASS |
Bill VanDegrift
|
|
|
Please call Dustin at ###-#### with any questions or concerns Phone #: ###-#### Inspection requested via web by Ben Davis final ok
|
Plumbing Rough-in | 7/22/2016 | 7/22/2016 | 7/22/2016 | P | PASS |
Jim Little
|
|
|
|
Plumbing Rough-in | 7/21/2016 | 7/22/2016 | 7/22/2016 | A | NR |
Jim Little
|
|
|
Please call Skyler with any questions ###-#### Phone #: ###-#### Inspection requested via web by Ben Davis
|
Water and/or Sewer | 7/15/2016 | 7/18/2016 | 7/18/2016 | A | PASS |
Daryl Spivey
|
|
|
Please call Dustin at ###-#### with any questions or concerns Phone #: ###-#### Inspection requested via web by Ben Davis
|
Groundwork | 7/14/2016 | 7/15/2016 | 7/15/2016 | P | FAIL |
Jim Little
|
|
|
Please call Dustin at ###-#### with any questions or concerns Phone #: ###-#### Inspection requested via web by Ben Davis >need a 10' head on dwv test's >need to expose tie in at main >need to use a double fixture ftg at back to back wc per 704.2
|