Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberPLM16-02815
StatusFinaled
Name PAIGE MECHANICAL GROUP INC
Site Address 350 N 9TH ST
Project Name 
Customer Number16.6403
ePlanReviewNo
Description
Alteration: Remodel restrooms, dwv, domestic water, fixtures
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final11/22/201611/28/201611/28/2016APASS
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Nicholas Paige
Final11/16/201611/17/201611/17/2016APART
DetailsDaryl Spivey
final on the 3rd floor. the 5th floor is still not done please call cody with any questions Phone #: ###-#### Inspection requested via web by Nicholas Paige
3rd floor ok for final...........ds
Plumbing Rough-in10/31/201610/31/201610/31/2016PDONE
DetailsDaryl Spivey
5th floor rough- Phone #: ###-#### Inspection requested via web by Nicholas Paige
Plumbing Rough-in10/28/201610/31/201610/31/2016APASS
DetailsDaryl Spivey
5th floor rough in Phone #: ###-#### Inspection requested via web by Nicholas Paige
Plumbing Rough-in10/21/201610/24/201610/24/2016APASS
DetailsDaryl Spivey
please call cody. as early as possible would be greatly appreciated so drywall may be hung.

thanks,
Phone #: ###-#### Inspection requested via web by Nicholas Paige
3rd floor rough in ok.........ds
Final9/15/20169/15/20169/15/2016PPART
DetailsDaryl Spivey
Partial Final for the 2nd floor and 4 th floors.... Phone #: ###-#### Inspection requested via web by Nicholas Paige
Lavs require tempering devices installed...............ds
Plumbing Rough-in8/11/20168/12/20168/12/2016APASS
DetailsDaryl Spivey
4th floor Phone #: ###-#### Inspection requested via web by Nicholas Paige
Plumbing Rough-in8/4/20168/5/20168/5/2016APASS
DetailsDaryl Spivey
2nd floor roughin Phone #: ###-#### Inspection requested via web by Nicholas Paige
2nd floor ok for cover.........ds