Final | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Eric Strole
|
|
|
9724 ENTER Phone #: ###-#### Inspection requested via web by Ann Marie Reyes
|
Plumbing Rough-in | 11/9/2016 | 11/10/2016 | 11/10/2016 | P | PASS |
Eric Strole
|
|
|
JOB # 18773 Phone #: ###-#### Inspection requested via web by Ann Marie Reyes
|
Plumbing Rough-in | 11/8/2016 | 11/9/2016 | 11/9/2016 | P | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Ann Marie Reyes-DWV test fail. Need to be 6" above flood level rim before tieing vents together .Missing nailplates and need to tast deck drain.
|
Groundwork | 9/19/2016 | 9/20/2016 | 9/20/2016 | A | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Ann Marie Reyes
|
Groundwork | 9/16/2016 | 9/19/2016 | 9/19/2016 | P | CANC |
Eric Strole
|
|
|
JOB # 18773. Phone #: ###-#### >> Inspection requested via web by Ann Marie Reyes Inspection cancelled from web by: Ann Marie Reyes
|
Plumbing Rough-in | 9/16/2016 | 9/19/2016 | 9/16/2016 | P | CANC |
Eric Strole
|
|
|
JOB # 18773. Phone #: ###-#### >> Inspection requested via web by Ann Marie Reyes Inspection cancelled from web by: Ann Marie Reyes
|
Groundwork | 9/15/2016 | 9/16/2016 | 9/16/2016 | P | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Ann Marie Reyes-Transition glue is only approved for outside the building from the building sewer to the building drain.
|