Final | 3/13/2017 | 3/17/2017 | 3/17/2017 | A | PASS |
Daryl Spivey
|
|
|
Customer will be home all am. Phone #: ###-#### Inspection requested via web by Scott Sparrell
|
Plumbing Rough-in | 10/19/2016 | 10/19/2016 | 10/19/2016 | P | PASS |
Daryl Spivey
|
|
|
Rough in is complete for new shower valves in master, main level bath and main bath upstairs. Drains were run tested after modified, water is on for new valves etc. Call for access code if no one on site. Vacant home with lock box. Phone #: ###-#### Inspection requested via web by Scott Sparrell
|
Plumbing Rough-in | 10/12/2016 | 10/14/2016 | 10/14/2016 | A | CANC |
Daryl Spivey
|
|
|
Master shower, main level bathroom shower, upstairs main bathroom tub/shower re-plumb. Remainder of fixtures on exisitng rough ins. will be at trim. Joel is contact. Phone #: ###-#### >> Inspection requested via web by Scott Sparrell Inspection cancelled from web by: Scott Sparrell
|
Plumbing Rough-in | 10/12/2016 | 10/12/2016 | 10/12/2016 | P | CANC |
Daryl Spivey
|
|
|
Plumbing rough in for master bathroom shower, main level bathroom shower. Remainder of job will be at trim at fixture change outs. Thanks. Joel is contact. Phone #: ###-#### >> Inspection requested via web by Scott Sparrell Inspection cancelled from web by: Scott Sparrell
|