Final | 1/6/2017 | 1/6/2017 | 1/6/2017 | P | PASS |
Bill VanDegrift
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Final | 12/27/2016 | 12/28/2016 | 12/28/2016 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Need hvb on boiler bib. Need to have all backflows tested. Need to run drain for rpba's. Temp final ok.
|
Plumbing Rough-in | 11/23/2016 | 11/28/2016 | 11/28/2016 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-In-wall rough-in for bathrooms pass.
|
Groundwork | 10/17/2016 | 10/18/2016 | 10/18/2016 | A | PASS |
Eric Strole
|
|
|
The approved plans are on site. it is back in for review but only for some drive way changes. Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Groundwork | 10/17/2016 | 10/17/2016 | 10/17/2016 | P | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Need approved plans on site for g/w inspection. Need full size c/o for 4" p-trap.
|