Final | 2/15/2018 | 2/16/2018 | 2/16/2018 | A | PASS |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
Final | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PART |
Bill VanDegrift
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER 1) temp occ ok 2) recieved med gas report( will email to me) 3) individual ice bin drain required on all ics makers 4) open up cabinet at floor sinks to allow overflow to flow out from under cabinets. 5) r.p. on dishwasher ok 6) rp required on warming wells
|
Final | 1/8/2018 | 1/8/2018 | 1/8/2018 | P | PART |
Dan Ediger
|
|
|
Bldg 300 complete with the expecption of the corroction notice to add a rp to the dishwasher.
|
Final | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Bathrooms ok. Checking on dishwasher and ro items.
|
Final | 12/12/2017 | 12/12/2017 | 12/12/2017 | P | FAIL |
Dan Ediger
|
|
|
Bldg 200. . All open room shower floors must drain an 1/8" to a 1/4" to the shower drian. Complete the tub install on the freestanding bathtub. Plumbing fixtures and backflows ok
|
Final | 12/11/2017 | 12/12/2017 | 12/12/2017 | A | CANC |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Rescheduled for afternoon
|
Plumbing Rough-in | 10/31/2017 | 11/1/2017 | 11/1/2017 | P | PART |
Dan Ediger
|
|
|
RUSSELL IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. MOB room dwv pressure test for wall plumbing .
|
Plumbing Rough-in | 10/19/2017 | 10/20/2017 | 10/20/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Water mains in hall ways in bldg 300. Passed pressure test
|
Med/Gas Systems | 10/4/2017 | 10/4/2017 | 10/4/2017 | A | PASS |
Dan Ediger
|
|
|
Pressure test 150# and 80 on vacuum.
|
Groundwork | 10/3/2017 | 10/4/2017 | 10/4/2017 | A | CANC |
Dan Ediger
|
|
|
RUSSELL IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Wrong job rescheduled to correct job.
|
Med/Gas Systems | 10/2/2017 | 10/3/2017 | 10/3/2017 | A | FAIL |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Med gas and natural gas piping are not part of this permit. A permit must be taken out for these items.
|
Plumbing Rough-in | 9/18/2017 | 9/19/2017 | 9/19/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. East wing bldg 300 ok to cover
|
Plumbing Rough-in | 9/11/2017 | 9/12/2017 | 9/12/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. North wing Blid 300 dwv and water walls ok to cover
|
Plumbing Rough-in | 9/6/2017 | 9/6/2017 | 9/6/2017 | P | PART |
Dan Ediger
|
|
|
JOB CONTACT - ROSS ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. West wing of bldg 300 ok to cover dwv
|
Plumbing Rough-in | 8/29/2017 | 8/30/2017 | 8/30/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. South corridor of bldg 300 ok
|
Plumbing Rough-in | 8/25/2017 | 8/28/2017 | 8/28/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER Buildings 100 and 200 water mains ok to cover.
|
Plumbing Rough-in | 8/9/2017 | 8/10/2017 | 8/10/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Roof drains on the west side of building 300 ok to cover
|
Plumbing Rough-in | 8/8/2017 | 8/8/2017 | 8/8/2017 | P | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER SE corner of buld. 300 roof drains ok
|
Plumbing Rough-in | 7/26/2017 | 7/27/2017 | 7/27/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Building 100 walls ok to cover. RP required on the ro system for the kitchen, No solder joints allowed on an stub-outs.
|
Plumbing Rough-in | 7/10/2017 | 7/11/2017 | 7/11/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Bldg 100 north roof drains ok.
|
Plumbing Rough-in | 7/6/2017 | 7/7/2017 | 7/7/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. South end of building 300 roof drains ok to cover
|
Plumbing Rough-in | 6/27/2017 | 6/28/2017 | 6/28/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. East wing of bldg 200.
|
Plumbing Rough-in | 6/22/2017 | 6/23/2017 | 6/23/2017 | A | PART |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Building 200: North wing ok. Less showers
|
Plumbing Rough-in | 6/16/2017 | 6/19/2017 | 6/19/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. West wing bldg 200
|
Plumbing Rough-in | 6/13/2017 | 6/14/2017 | 6/14/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Nailplate the risers, run 2" vent from the shower, west end. Pressure test ok
|
Roof Drains | 6/7/2017 | 6/7/2017 | 6/7/2017 | P | PART |
Dan Ediger
|
|
|
Bldg #200 ok to cover roof drains
|
Plumbing Rough-in | 6/6/2017 | 6/7/2017 | 6/7/2017 | A | NR |
Dan Ediger
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
Plumbing Rough-in | 6/2/2017 | 6/5/2017 | 6/5/2017 | A | PART |
Dan Ediger
|
|
|
JOB CONTACT IS ROSS ANDERSON Phone #: ###-#### Inspection requested via web by BECCA DUMMER. South corridor roof drain on the western most building
|
Groundwork | 4/11/2017 | 4/12/2017 | 4/12/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. southwest bathrooms east bldg
|
Groundwork | 4/11/2017 | 4/11/2017 | 4/11/2017 | P | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. North-east end of bldg.
|
Groundwork | 4/5/2017 | 4/5/2017 | 4/5/2017 | P | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. completes west wing ok to cover.
|
Groundwork | 4/3/2017 | 4/4/2017 | 4/4/2017 | A | PASS |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Northwest rr ok to cover up to center of building
|
Groundwork | 3/30/2017 | 3/31/2017 | 3/31/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. south-west two baths bldg 300 ok to cover
|
Groundwork | 3/28/2017 | 3/29/2017 | 3/29/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. bldg 300. sw bath and east main drian. ok
|
Groundwork | 3/27/2017 | 3/28/2017 | 3/28/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Main drain west side of bldg 300
|
Groundwork | 3/22/2017 | 3/23/2017 | 3/23/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. kitchen and grease ok to cover
|
Groundwork | 3/20/2017 | 3/21/2017 | 3/21/2017 | P | PART |
Bill VanDegrift
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER north half of the center section to the salon sink test ok plus the restroom group on the south east side, east of the kitchen. and the discharge side of the grease interceptor with vent ok to cover.
|
Groundwork | 3/15/2017 | 3/16/2017 | 3/16/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. West corridor groundwork complete
|
Groundwork | 3/14/2017 | 3/15/2017 | 3/15/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. West corridor all but the last 3 rr in the sw corner
|
Groundwork | 3/9/2017 | 3/10/2017 | 3/10/2017 | P | PART |
Dan Ediger
|
|
|
CHRIS IS THE ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Building 100 main drain trunk line ok to cover
|
Groundwork | 3/3/2017 | 3/6/2017 | 3/6/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. sw corner bathroom groups
|
Groundwork | 2/15/2017 | 2/16/2017 | 2/16/2017 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Southeast bathroom group ok to cover. Backfill material has been corrected.
|
Groundwork | 2/14/2017 | 2/15/2017 | 2/15/2017 | A | PART |
Bill VanDegrift
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER six restroom groups far north west corner of project test ok, talked to Chriss Buss about bedding under the piping, seems to be frozen wet mud, he will verify bedding.
|
Groundwork | 12/12/2016 | 12/13/2016 | 12/13/2016 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-####. Phone #: ###-#### Inspection requested via web by BECCA DUMMER. west end main drain turns east and ties into the east trunk line
|
Groundwork | 12/6/2016 | 12/7/2016 | 12/7/2016 | A | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. East main trunk line ground work ok.
|
Groundwork | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PART |
Dan Ediger
|
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Pressure test on 4" copper water service inlet.
|