Final | 7/27/2017 | 7/27/2017 | 7/27/2017 | P | PASS |
Dan Ediger
|
|
|
All work under this permit is complete
|
Final | 7/25/2017 | 7/26/2017 | 7/26/2017 | A | CANC |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Frank Young
|
Final | 7/5/2017 | 7/5/2017 | 7/5/2017 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Frank Young-Trim final ok. Will be adding a floor drain in basement by solor tanks. Will add to permit and call for inspection.
|
Plumbing Rough-in | 12/27/2016 | 12/28/2016 | 12/28/2016 | A | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Frank Young. Rough plumbing good to cover. Solar contractor needs to provide a design and pull permit for the work done
|