Final | 3/30/2017 | 3/31/2017 | 3/31/2017 | P | PASS |
Bill VanDegrift
|
|
|
Final inspection to finish partial. Builder has said that all finishes will be complete. Phone #: ###-#### Inspection requested via web by Jason Brashears
|
Final | 3/28/2017 | 3/29/2017 | 3/29/2017 | P | PART |
Eric Strole
|
|
|
Plumbing and gas final. Phone #: ###-#### Inspection requested via web by Jason Brashears-Need to install a dbca on ice maker. Need to install all equipment. Temp final ok.
|
Other | 3/7/2017 | 3/8/2017 | 3/8/2017 | A | PASS |
Eric Strole
|
|
|
Rough-in gas piping, air test for 2 pound system. Phone #: ###-#### Inspection requested via web by Jason Brashears-60 lb gas test pass.
|
Plumbing Rough-in | 3/4/2017 | 3/6/2017 | 3/6/2017 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Jason Brashears-Inwall rough-in pass.
|
Groundwork | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Jason Brashears
|