Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberPLM17-00614
StatusFinaled
Name WARNER CONSTRUCTION
Site Address 8000 S FEDERAL WAY
Project NameMicron B51 R & D Facility
Customer Number395
ePlanReviewNo
Description
New: Full installation of sewer, water and storm drain systems to facilitate operations of building 51
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final8/30/20188/31/20188/31/2018APASS
DetailsEric Strole
Requesting final close out inspection for Micron Building 51 Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer7/13/20187/16/20187/16/2018APASS
DetailsEric Strole
Installation of sewer lift station. East side of building 51. Been Scott primary contact on site. Phone #: ###-#### Inspection requested via web by Craig Fischer
PLM-Aging Inspection5/22/20185/22/20185/22/2018 PART
DetailsEric Strole
PLM-Aging Inspection2/20/20182/20/20182/20/2018 PART
DetailsEric Strole
wip
Water and/or Sewer11/21/201711/21/201711/21/2017PCANC
DetailsEric Strole
South East of building 51 and T-CUP facility. Installation of sewer manhole tie-in and 8in sewer line to the South. Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer11/20/201711/21/201711/21/2017ACANC
DetailsEric Strole
South East of building 51 and T-CUP facility. Installation of sewer manhole tie-in and 8in sewer line to the South. Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer11/20/201711/20/201711/20/2017PNR
DetailsEric Strole
South East of building 51 and T-CUP facility. Installation of sewer manhole tie-in and 8in sewer line to the South. Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer11/17/201711/20/201711/20/2017ANR
DetailsEric Strole
South East of building 51 and T-CUP facility. Installation of sewer manhole tie-in and 8in sewer line to the South. Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer10/30/201710/31/201710/31/2017APART
DetailsEric Strole
East side of building 51. Connection of 3in sewer line to existing sewer line. Ben Scott onsite Phone #: ###-#### Inspection requested via web by Craig Fischer-Pressure sewer from tie-in to existing up to sump location ok to cover. Still need sump.
Storm Drains9/25/20179/26/20179/26/2017APART
DetailsEric Strole
North East corner of building 51, connect 8in RDL''s to main storm drain line Phone #: ###-#### Inspection requested via web by Craig Fischer-All underground storm drain to roof drain complete.
Water and/or Sewer7/25/20177/26/20177/26/2017PPART
DetailsEric Strole
West side of building 51. Pressure test on 8in potable water line. Phone #: ###-#### Inspection requested via web by Craig Fischer-8" water main and 4" water main into building test pass.
Water and/or Sewer7/20/20177/21/20177/21/2017PPART
DetailsEric Strole
West side of building 51. Continue 8in potable water from North heading South to tie in. Phone #: ###-#### Inspection requested via web by Craig Fischer-Section of 8" water main installed ok to cover, still needs tested.
Water and/or Sewer7/19/20177/20/20177/20/2017PNR
DetailsEric Strole
West side of building 51. Continue 8in potable water from North heading South to tie in. Phone #: ###-#### Inspection requested via web by Craig Fischer-Chip chip chip no gain
Water and/or Sewer7/19/20177/20/20177/20/2017ACANC
DetailsEric Strole
West side of building 51. Continue 8in potable water from North heading South to tie in. Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer7/19/20177/19/20177/19/2017PPART
DetailsEric Strole
West side of building 51. Continue 8in potable water from North heading South to tie in. Phone #: ###-#### Inspection requested via web by Craig Fischer-Section of 8" water main installed ok to cover, still needs tested.
Water and/or Sewer7/7/20177/10/20177/10/2017PPART
DetailsEric Strole
8" water main up to south end of building 36.
Water and/or Sewer7/7/20177/7/20177/7/2017PPART
DetailsEric Strole
West side of Building 51. Continuation of 8in potable water from North to South connection Phone #: ###-#### Inspection requested via web by Craig Fischer-Section of water main installed ok to cover, still needs tested.
Water and/or Sewer7/6/20177/7/20177/7/2017APART
DetailsEric Strole
West side of Building 51. Continuation of 8in potable water from North to South connection Phone #: ###-#### Inspection requested via web by Craig Fischer-Section of water main installed ok to cover, still needs tested.
Water and/or Sewer6/30/20176/30/20176/30/2017PPART
DetailsEric Strole
North-West corner building 51. Connection of 12in Storm Drain line from building 50 into existing manhole, tie-in 8in storm drain line from building 51 into 12in line. Phone #: ###-#### Inspection requested via web by Craig Fischer-Section complete ok to cover.
Water and/or Sewer6/28/20176/29/20176/30/2017PPART
DetailsEric Strole
North-West corner building 51. Connection of 12in Storm Drain line from building 50 into existing manhole, tie-in 8in storm drain line from building 51 into 12in line. Phone #: ###-#### Inspection requested via web by Craig Fischer-Section complete ok to cover, still needs tested.
Water and/or Sewer6/28/20176/29/20176/29/2017APART
DetailsEric Strole
North-West corner building 51. Connection of 12in Storm Drain line from building 50 into existing manhole, tie-in 8in storm drain line from building 51 into 12in line. Phone #: ###-#### Inspection requested via web by Craig Fischer-Digging
Water and/or Sewer6/28/20176/29/20176/29/2017PCANC
DetailsEric Strole
Continuation of 12in storm drain line heading North. Installing stubs for 4in roof leader connections to 12in main line. Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer6/28/20176/29/20176/29/2017ACANC
DetailsEric Strole
South-East corner of building 51. Continuation of 12in storm drain line heading North. Installing stubs for 4in roof leader connections to 12in main line. Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer6/27/20176/28/20176/28/2017PPART
DetailsEric Strole
South-East corner of building 51. Continuation of 12in storm drain line heading North. Installing stubs for 4in roof leader connections to 12in main line. Phone #: ###-#### Inspection requested via web by Craig Fischer-Section complete ok to cover, still needs tested.
Water and/or Sewer6/27/20176/28/20176/28/2017PCANC
DetailsEric Strole
North-West corner building 51. Connection of 12in Storm Drain line from building 50 into existing manhole, tie-in 8in storm drain line from building 51 into 12in line. Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer6/26/20176/27/20176/27/2017PNR
DetailsEric Strole
South-East corner of building 51. Continuation of 12in storm drain line heading North. Installing stubs for 4in roof leader connections to 12in main line. Phone #: ###-#### Inspection requested via web by Craig Fischer-No progress
Water and/or Sewer6/26/20176/27/20176/27/2017PNR
DetailsEric Strole
West side of building 51. Continuation of 8in potable water heading South. Phone #: ###-#### Inspection requested via web by Craig Fischer-No progress
Water and/or Sewer6/26/20176/27/20176/27/2017PNR
DetailsEric Strole
North-West corner building 51. Connection of 12in Storm Drain line from building 50 into existing manhole, tie-in 8in storm drain line from building 51 into 12in line. Phone #: ###-#### Inspection requested via web by Craig Fischer-No progress
Water and/or Sewer6/26/20176/27/20176/27/2017APART
DetailsEric Strole
South-East corner of building 51. Continuation of 12in storm drain line heading North. Installing stubs for 4in roof leader connections to 12in main line. Phone #: ###-#### Inspection requested via web by Craig Fischerr-Section complete ok to cover, still needs tested.
Storm Drains6/23/20176/26/20176/26/2017PPART
DetailsEric Strole
South-East corner of building 51. Continuation of 12in storm drain line heading North. Installing stubs for 4in roof leader connections to 12in main line. Phone #: ###-#### Inspection requested via web by Craig Fischer-Section complete ok to cover, still needs tested.
Water and/or Sewer6/23/20176/26/20176/26/2017ANR
DetailsEric Strole
West side of building 51. Continuation of 8in potable water heading South. Phone #: ###-#### Inspection requested via web by Craig Fischer
Storm Drains6/23/20176/26/20176/26/2017ANR
DetailsEric Strole
North-West corner building 51. Connection of 12in Storm Drain line from building 50 into existing manhole, tie-in 8in storm drain line from building 51 into 12in line. Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer6/21/20176/22/20176/22/2017PCANC
DetailsEric Strole
Water and/or Sewer6/21/20176/22/20176/22/2017ACANC
DetailsEric Strole
Water and/or Sewer6/21/20176/21/20176/21/2017PCANC
DetailsEric Strole
Water and/or Sewer6/20/20176/21/20176/21/2017APART
DetailsEric Strole
4" sewer tie-in and test west side pass.
Water and/or Sewer6/19/20176/20/20176/20/2017PPART
DetailsEric Strole
20' installed.
Water and/or Sewer6/19/20176/20/20176/20/2017ANR
DetailsEric Strole
Water and/or Sewer6/19/20176/19/20176/19/2017PDONE
DetailsEric Strole
West side of building 51. Continue 4in sewer to tie in with existing sewer line Phone #: ###-#### Inspection requested via web by Craig Fischer-Conferance on sewer
Water and/or Sewer6/16/20176/16/20176/16/2017APART
DetailsEric Strole
South East corner of building 51, connection of 8in potable water to building Phone #: ###-#### Inspection requested via web by Craig Fischer-Water supply south/east corner test pass.
Water and/or Sewer6/12/20176/13/20176/13/2017PPART
DetailsBill VanDegrift
water up to the building, need plumber to tie in next.
Water and/or Sewer6/9/20176/12/20176/12/2017PPART
DetailsBill VanDegrift
South East corner of building 51. Continuation of 8" water main. Phone #: ###-#### Inspection requested via web by Craig Fischer working on the water servces south east corner
Water and/or Sewer6/9/20176/9/20176/9/2017PNR
DetailsEric Strole
South East corner of building 51. Continuation of 8" water main. Phone #: ###-#### Inspection requested via web by Craig Fischer-No gain
Water and/or Sewer6/8/20176/9/20176/9/2017APART
DetailsEric Strole
South East corner of building 51. Connecting 8in RDL to 12in Storm Drain running North out of manhole. Phone #: ###-#### Inspection requested via web by Craig Fischer-Section of storm drain installed ok to cover, Still needs tested.
Water and/or Sewer6/7/20176/8/20176/8/2017ANR
DetailsEric Strole
South East corner of building 51. Connecting 8in RDL to 12in Storm Drain running North out of manhole. Phone #: ###-#### Inspection requested via web by Craig Fischer
Storm Drains6/7/20176/7/20176/7/2017PDONE
DetailsEric Strole
South East corner of building 51. Connecting 8in RDL to 12in Storm Drain running North out of manhole. Phone #: ###-#### Inspection requested via web by Craig Fischer-Conferance on stormdrain and water main.
Storm Drains6/6/20176/7/20176/7/2017ANR
DetailsEric Strole
South East corner of building 51. Connecting 8in RDL to 12in Storm Drain running North out of manhole. Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer5/11/20175/12/20175/12/2017PPART
DetailsEric Strole
Stormdrain south/east side installed.
Water and/or Sewer5/11/20175/12/20175/12/2017ANR
DetailsEric Strole
Water and/or Sewer5/10/20175/11/20175/11/2017APART
DetailsEric Strole
220' of 8" water main installed so far. All needs tested.
Water and/or Sewer5/9/20175/10/20175/10/2017PPART
DetailsEric Strole
180' of 8" water main installed
Water and/or Sewer5/9/20175/10/20175/10/2017ACANC
DetailsEric Strole
Water and/or Sewer5/9/20175/9/20175/9/2017PCANC
DetailsEric Strole
No progress
Water and/or Sewer5/8/20175/9/20175/9/2017APART
DetailsEric Strole
Installing Potable Water between South East corner of building 51 and previously installed 8in potable water by N2 Plant Phone #: ###-#### Inspection requested via web by Craig Fischer-140' of 8" water main installed from N2 building side to building 51 installed so far. Will install saddle on same line for 2" PE service for teacup building. All piping still needs tested.
Water and/or Sewer5/5/20175/5/20175/5/2017PCANC
DetailsEric Strole
No gain
Water and/or Sewer5/3/20175/4/20175/4/2017PPART
DetailsEric Strole
126' of 8" water main installed.
Water and/or Sewer5/3/20175/4/20175/4/2017ACANC
DetailsEric Strole
Water and/or Sewer5/2/20175/3/20175/3/2017PPART
DetailsEric Strole
4in potable water line, North West area of building 51 Phone #: ###-#### Inspection requested via web by Craig Fischer-106' installed with blue tracer wire.
Water and/or Sewer5/2/20175/3/20175/3/2017APART
DetailsEric Strole
4in potable water line, North West area of building 51 Phone #: ###-#### Inspection requested via web by Craig Fischer-80' of 8" installed. Need a blue18 gauge tracer wire.
Water and/or Sewer5/2/20175/2/20175/2/2017PPART
DetailsEric Strole
4in potable water line, North West area of building 51 Phone #: ###-#### Inspection requested via web by Craig Fischer-26' of 8" water main installed.
Water and/or Sewer5/1/20175/2/20175/2/2017ACANC
DetailsEric Strole
4in potable water line, North West area of building 51 Phone #: ###-#### Inspection requested via web by Craig Fischer-No gain
Water and/or Sewer4/28/20175/1/20175/1/2017APART
DetailsEric Strole
4in potable water line, North West area of building 51 Phone #: ###-#### Inspection requested via web by Craig Fischer-4" water main from building out to valve box installed. Need to install 8" water main from valve box to 8' existing main and test all 4" & 8" when complete.
Water and/or Sewer4/27/20174/28/20174/28/2017PPART
DetailsEric Strole
4in potable water line, North West area of building 51 Phone #: ###-#### Inspection requested via web by Craig Fischer-1st 40' of 4" water supply from building out north west side installed. Still need test.
Water and/or Sewer4/26/20174/27/20174/27/2017ANR
DetailsEric Strole
4in potable water line, North West area of building 51 Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer4/18/20174/19/20174/19/2017PCANC
DetailsEric Strole
North West corner of building 51. 8in roof drain line from building 51, connecting to 12in roof drain line from building 50 and continuing to existing storm drain manhole Phone #: ###-#### Inspection requested via web by Craig Fischer
Storm Drains4/17/20174/18/20174/18/2017PCANC
DetailsEric Strole
North West corner of building 51. 8in roof drain line from building 51, connecting to 12in roof drain line from building 50 and continuing to existing storm drain manhole Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer3/23/20173/24/20173/24/2017APART
DetailsEric Strole
Potable Water at bore pit, South West corner of Micron Bld 51 project Phone #: ###-#### Inspection requested via web by Craig Fischer-168' installed so far. Still need tested.
Water and/or Sewer3/23/20173/24/20173/24/2017PCANC
DetailsEric Strole
Potable Water at bore pit, South West corner of Micron Bld 51 project Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer3/23/20173/24/20173/23/2017PCANC
DetailsEric Strole
Potable Water at bore pit, South West corner of Micron Bld 51 project Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer3/23/20173/23/20173/23/2017ACANC
DetailsEric Strole
Potable Water at bore pit, South West corner of Micron Bld 51 project Phone #: ###-#### Inspection requested via web by Craig Fischer
Water and/or Sewer3/23/20173/23/20173/23/2017PPART
DetailsEric Strole
Potable Water at bore pit, South West corner of Micron Bld 51 project Phone #: ###-#### Inspection requested via web by Craig Fischer-148' of 8' water service installed so far.
Water and/or Sewer3/22/20173/23/20173/23/2017APART
DetailsEric Strole
8" Potable Water at bore pit, South West corner of Micron Bld 51 project Phone #: ###-#### Inspection requested via web by Craig Fischer-88' of 8' water service installed so far.
Storm Drains3/13/20173/13/20173/13/2017PCANC
DetailsEric Strole
This section of storm drains is for gutters. Requires no inspection from plumbing.
Water and/or Sewer3/8/20173/9/20173/9/2017PCANC
DetailsEric Strole
Water and/or Sewer3/8/20173/9/20173/9/2017ANR
DetailsEric Strole
Still chipping rock
Water and/or Sewer3/7/20173/8/20173/8/2017PPART
DetailsEric Strole
1st 40' of storm drain from building out installed so far.
Water and/or Sewer3/8/20173/9/20173/8/2017ACANC
DetailsEric Strole
Water and/or Sewer3/7/20173/8/20173/8/2017ACANC
DetailsEric Strole
Water and/or Sewer3/7/20173/7/20173/7/2017PPART
DetailsEric Strole
Up to 80' installed. Still need tested.
Water and/or Sewer3/7/20173/7/20173/7/2017APART
DetailsEric Strole
40' of 4" sewer out of building 51 installed so far. Still need tested.