Final | 11/3/2017 | 11/8/2017 | 11/8/2017 | A | PASS |
Dan Ediger
|
|
|
Re-pipe under 3 pots. To include 2 high temp 1 inch valves and also a back flow preventer. Phone #: ###-#### Inspection requested via web by Shane Loar
|
PLM-Aging Inspection | 11/3/2017 | 11/3/2017 | 11/3/2017 | | PEND |
Dan Ediger
|
|
|
contractor to schedule
|
Final | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | PART |
Dan Ediger
|
|
|
Final Inspection - Harris contact onsite Phone #: ###-#### Inspection requested via web by Shane Loar. Gas pressure test ok
|
Other | 4/25/2017 | 4/25/2017 | 4/25/2017 | P | NR |
Dan Ediger
|
|
|
Rough in of gas line for boiler. Need late morning/early afternoon Phone #: ###-#### Inspection requested via web by Shane Loar. complete the installation, pull a permit for the rp and have it certified, and gas piping pressure test to 20 psi
|