Final | 7/14/2017 | 7/14/2017 | 7/14/2017 | P | PASS |
Dan Ediger
|
|
|
|
Plumbing Rough-in | 7/14/2017 | 7/14/2017 | 7/14/2017 | P | CANC |
Dan Ediger
|
|
|
|
Final | 6/28/2017 | 6/28/2017 | 6/28/2017 | P | PART |
Dan Ediger
|
|
|
Just looking for partial final so they can move in upstairs where break room is. First floor rough in to follow demo of first floor break sink in two weeks. Thanks Phone #: ###-####. Inspection requested via web by Ben Taylor Upstairs breakroom sink ok
|
Plumbing Rough-in | 5/24/2017 | 5/25/2017 | 5/25/2017 | A | PART |
Dan Ediger
|
|
|
Partial rough in just to get out of walls for phase one (second floor). Call ahead and i will get general contractor to meet you at front desk. Phone #: ###-#### Inspection requested . via web by Ben Taylor. DWV and water ok to cover on the second floor
|