Final | 7/19/2017 | 7/19/2017 | 7/19/2017 | A | PASS |
Daryl Spivey
|
|
|
plumbing completeed.........ds
|
Plumbing Rough-in | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | PASS |
Daryl Spivey
|
|
|
Joe Phone #: ###-#### last 5 rooms on 5th floor and 1 room on 3rd floor ok.........ds
|
Plumbing Rough-in | 7/13/2017 | 7/13/2017 | 7/13/2017 | P | PART |
Daryl Spivey
|
|
|
Joe Phone #: ###-#### 6 rooms 5th floor ok.........ds
|
Plumbing Rough-in | 6/27/2017 | 6/28/2017 | 6/28/2017 | A | PART |
Daryl Spivey
|
|
|
Joe Phone #: ###-#### 4 rooms 4th floor ok.......ds
|
Plumbing Rough-in | 6/21/2017 | 6/21/2017 | 6/21/2017 | P | PART |
Daryl Spivey
|
|
|
Joe Phone #: ###-#### last 5 rooms on 3rd floor done.........ds
|
Plumbing Rough-in | 6/13/2017 | 6/14/2017 | 6/14/2017 | A | PART |
Daryl Spivey
|
|
|
Joe Phone #: ###-#### 5 more done.........17 total.........ds
|
Plumbing Rough-in | 6/6/2017 | 6/7/2017 | 6/7/2017 | A | PART |
Daryl Spivey
|
|
|
Joe Phone #: ###-#### 4 rooms done......8 total..............ds
|
Plumbing Rough-in | 5/30/2017 | 5/31/2017 | 5/31/2017 | A | PART |
Daryl Spivey
|
|
|
Joe Phone #: ###-#### showers for 3 rooms on 1st floor done.......ds
|