Final | 2/14/2018 | 2/14/2018 | 2/14/2018 | P | PASS |
Dan Ediger
|
|
|
we prefer later in the day if possible.
thanks, Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Final | 2/1/2018 | 2/2/2018 | 2/2/2018 | A | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige. Signed Temp Occ. Builder needs to verify if rr are ADA required with the Arch.
|
Final | 1/17/2018 | 1/18/2018 | 1/18/2018 | A | PART |
Bill VanDegrift
|
|
|
partial final for Idaho Youth ranch portion of Belmont shell and core. Phone #: ###-#### Inspection requested via web by Nicholas Paige temp occ for shell and core, Youth Ranch. added a mop sink in ACE space but I believe that should be on the TI permit for ACE
|
Groundwork | 10/25/2017 | 10/26/2017 | 10/26/2017 | A | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige. Ground work to the sewage ejector and a 60' 4" drain extention into the Dead On space ok to cover
|
Groundwork | 10/16/2017 | 10/17/2017 | 10/16/2017 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Trunkline into 2nd to last space west side ok to cover with clean fill.
|
Plumbing Rough-in | 10/16/2017 | 10/16/2017 | 10/16/2017 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Plumbing Rough-in | 9/27/2017 | 9/28/2017 | 9/28/2017 | A | PASS |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Groundwork | 9/1/2017 | 9/1/2017 | 9/1/2017 | P | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige. Gw ok to cover for the Youth Ranch RR
|
Groundwork | 8/8/2017 | 8/9/2017 | 8/9/2017 | A | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige. Gw for the Church rr ok to cover ne corner
|