Final | 5/31/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Final | 5/31/2018 | 6/1/2018 | 5/31/2018 | A | CANC |
Eric Strole
|
|
|
Phone #: ###-#### >> Inspection requested via web by Nicholas Paige Inspection cancelled from web by: Nicholas Paige
|
Final | 5/29/2018 | 5/30/2018 | 5/30/2018 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Need to install rp's before filter systems on ice machines & seperate fuel & sewer vents for fuel interceptor. Temp final ok.
|
Plumbing Rough-in | 1/17/2018 | 1/18/2018 | 1/18/2018 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Bathroom east side pass.
|
Plumbing Rough-in | 1/5/2018 | 1/8/2018 | 1/8/2018 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Gang bath ok to cover. North bath ok to cover walls. North bath need to install a hammer arrester. Need to hookup overhead water line to ice machines.
|
Plumbing Rough-in | 12/18/2017 | 12/19/2017 | 12/19/2017 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Breakroom sink north/west area ok to cover.
|
Plumbing Rough-in | 12/14/2017 | 12/14/2017 | 12/14/2017 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-3" overhead waterline ok to insulate.
|
Plumbing Rough-in | 12/12/2017 | 12/13/2017 | 12/13/2017 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-2-3" vents ok to cover.
|
Groundwork | 11/13/2017 | 11/13/2017 | 11/13/2017 | P | PART |
Bill VanDegrift
|
|
|
last of the trench drains in the large building east end.
|
Groundwork | 11/2/2017 | 11/6/2017 | 11/6/2017 | P | CANC |
Eric Strole
|
|
|
Please call Ryan ###-#### Thanks Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
Groundwork | 10/17/2017 | 10/18/2017 | 10/18/2017 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Interceptor vents pass.
|
Groundwork | 10/16/2017 | 10/16/2017 | 10/16/2017 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Section complete ok to cover.
|
Groundwork | 9/28/2017 | 9/29/2017 | 9/29/2017 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-West end g/w pass.
|
Groundwork | 9/26/2017 | 9/27/2017 | 9/27/2017 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Section of g/w to fuel interceptor pass
|
Water and/or Sewer | 9/21/2017 | 9/21/2017 | 9/21/2017 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Waterline stub into & out of building pass.
|
Groundwork | 9/18/2017 | 9/21/2017 | 9/21/2017 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-Bathroom group east side pass.
|
Groundwork | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige-West end 4" trunkline and 3" flr drain pass.
|