PLM-Aging Inspection | 7/17/2018 | 7/17/2018 | 7/23/2018 | | PASS |
Dan Ediger
|
|
|
|
Final | 7/23/2018 | 7/23/2018 | 7/23/2018 | P | PASS |
Dan Ediger
|
|
|
Part of the completed permit.
|
Groundwork | 11/6/2017 | 11/7/2017 | 11/8/2017 | P | NR |
Bill VanDegrift
|
|
|
LATE PM - If question call Mike @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann bld permit not issued yet, no code issues with the gw, deleted 4" waste to sink on south side of the building and the floor drain by the furnaces is 2" instead of 3". talked to the owner and those changes are what he wants and approves. they will call it back in when the bld permit is issued.
|
Water and/or Sewer | 10/19/2017 | 10/20/2017 | 10/20/2017 | A | PART |
Dan Ediger
|
|
|
underground sewer main and water service. Phone #: ###-#### Inspection requested via web by Stacia Haumann. Certify backflow and change the drain down valve to an approved valve .ok to cover up to the backflow assembly
|