Water and/or Sewer | 3/14/2018 | 3/14/2018 | 3/14/2018 | P | PASS |
Dan Ediger
|
|
|
|
DOC - Permit Finaled | 3/14/2018 | 3/14/2018 | 3/14/2018 | P | PASS |
Dan Ediger
|
|
|
|
Water and/or Sewer | 12/19/2017 | 12/19/2017 | 12/19/2017 | P | PASS |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum.Island yard hydrants are installed. Could not witness connection joinst-backfilled and preped for concrete
|
Water and/or Sewer | 12/14/2017 | 12/15/2017 | 12/15/2017 | A | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum. Water service pressure test passed and tracer wire installed. Final on yard hydrant install
|
Water and/or Sewer | 12/8/2017 | 12/11/2017 | 12/11/2017 | A | FAIL |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum. Install 18ga blue tracer wire from the meter to the building connection and to both fuel station yard hydrants. Termanal wire ends to be exposed above grade.
|
Storm Drains | 11/30/2017 | 12/1/2017 | 12/1/2017 | A | PART |
Bill VanDegrift
|
|
|
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum fuel islands
|
Water and/or Sewer | 11/17/2017 | 11/20/2017 | 11/20/2017 | A | PASS |
Dan Ediger
|
|
|
Storm Drain Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
|
Water and/or Sewer | 11/17/2017 | 11/17/2017 | 11/17/2017 | P | FAIL |
Dan Ediger
|
|
|
Roof drain leaders. Use transition glue or Fernco couplings to transition from pvc to abs. Use fittings to make grade and angle adjustments not Fernco couplings.
|
Water and/or Sewer | 11/16/2017 | 11/17/2017 | 11/17/2017 | A | NR |
Dan Ediger
|
|
|
Storm Drain Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
|
Water and/or Sewer | 11/7/2017 | 11/7/2017 | 11/7/2017 | P | PART |
Dan Ediger
|
|
|
Vents on Sand ; Grease for Sewer Phone #: ###-#### Inspection requested via web by Katherine Creekbaum. Grease interceptor complete ok to cover.
|
Water and/or Sewer | 11/1/2017 | 11/1/2017 | 11/1/2017 | P | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum. The tank passed the 24hr test. Sewer held test and can be backfilled. The 3" grease int. vent needs ran and tested prior to backfill of the vent.
|
Water and/or Sewer | 10/30/2017 | 10/30/2017 | 10/30/2017 | P | PART |
Bill VanDegrift
|
|
|
interceptor test ok, will grout inlet and outlet, and relay the sewer
|
Water and/or Sewer | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | NR |
Dan Ediger
|
|
|
Sewer Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
|
Other | 10/27/2017 | 10/27/2017 | 10/27/2017 | P | FAIL |
Dan Ediger
|
|
|
Started 24hr test on the grease interceptor. Notified the contractor that the tank is leaking.
|