Final | 7/6/2018 | 7/9/2018 | 7/9/2018 | A | PASS |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by Glenn Kelso
|
Water and/or Sewer | 6/5/2018 | 6/6/2018 | 6/6/2018 | A | PART |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by Glenn Kelso water serv and pvb ok...pvb needs tested...........ds
|
Plumbing Rough-in | 2/27/2018 | 2/28/2018 | 2/28/2018 | P | PASS |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by Glenn Kelso
|
Water and/or Sewer | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | PART |
Daryl Spivey
|
|
|
Inspection requested via web by Glenn Kelso sewer ok..........ds
|
Groundwork | 10/25/2017 | 10/27/2017 | 10/27/2017 | A | PASS |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by Glenn Kelso
|