Final | 3/13/2018 | 3/14/2018 | 3/14/2018 | A | PASS |
Daryl Spivey
|
|
|
Joe ###-#### no occ card on site..........ds
|
Final | 3/12/2018 | 3/13/2018 | 3/13/2018 | P | PART |
Daryl Spivey
|
|
|
Joe-would like as late as possible Phone #: ###-#### temp occ. ok.........ds
|
Plumbing Rough-in | 12/21/2017 | 12/22/2017 | 12/22/2017 | P | PASS |
Bill VanDegrift
|
|
|
Plumbing Rough-in Above Ground Inspection. Phone #: ###-#### Inspection requested via web by Joe Gamez ri ok
|
Plumbing Rough-in | 11/27/2017 | 11/28/2017 | 11/28/2017 | P | CANC |
Bill VanDegrift
|
|
|
Underground, late afternoon - Joe Phone #: ###-#### this was a gw
|
Groundwork | 11/28/2017 | 11/28/2017 | 11/28/2017 | P | PASS |
Bill VanDegrift
|
|
|
Underground, late afternoon - Joe Phone #: ###-#### gw ok waste piping tied to existing grading north instead of south like the plans.
|