Final | 4/14/2019 | 4/15/2019 | 4/15/2019 | P | PASS |
Eric Strole
|
|
|
Door will be unlocked by contractor. Space if vacant, need final so they can move in. Phone #: ###-#### Inspection requested via web by Scott Sparrell
|
Final | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | NH |
Eric Strole
|
|
|
Rex is contractor for access. Will be open today for inspection. Phone #: ###-#### Inspection requested via web by Scott Sparrell-No access, left notice
|
PLM-Aging Inspection | 1/14/2019 | 1/14/2019 | 1/14/2019 | | PART |
Eric Strole
|
|
|
No calls
|
PLM-Aging Inspection | 10/15/2018 | 10/15/2018 | 10/15/2018 | | PART |
Eric Strole
|
|
|
No calls
|
Final | 7/16/2018 | 7/16/2018 | 7/16/2018 | P | PART |
Eric Strole
|
|
|
Job is complete for plumbing trim. All sinks are set, caulked and ready. Call Hasib for code for access. Phone #: ###-#### Inspection requested via web by Scott Sparrell-Need to add expantion tank and have dbca tested.
|
Plumbing Rough-in | 4/20/2018 | 4/20/2018 | 4/20/2018 | P | PASS |
Eric Strole
|
|
|
Re-inspection ready, added floor drain, vents etc. as requested. Hasib is contact. Ready late am, pm. Phone #: ###-#### Inspection requested via web by Scott Sparrell
|
Plumbing Rough-in | 4/17/2018 | 4/18/2018 | 4/18/2018 | A | FAIL |
Eric Strole
|
|
|
Top out rough in for floor sink, two hand wash sinks, prep sink, 3 compartment sink. Under test on venting/drains waters. Phone #: ###-#### Inspection requested via web by Scott Sparrell-Need to lower flr sink to be flush with floor or add flr drain. Need to run vent for grease trap and fix backgrade on 2" drain.
|
Groundwork | 3/30/2018 | 3/30/2018 | 3/30/2018 | A | PASS |
Eric Strole
|
|
|
Groundwork for kitchen addition with end of line clean out, floor sink, hand wash rough in west wall. Under test. Lock box code is 1297. Hasib is contact. Phone #: ###-#### Inspection requested via web by Scott Sparrell
|
Groundwork | 12/6/2017 | 12/6/2017 | 12/6/2017 | P | FAIL |
Eric Strole
|
|
|
Hasib is lead on job, groundwork for a floor sink, hand wash sink plumbing in slab, Under test and ready for inspection. General will be on site all day. Phone #: ###-#### Inspection requested via web by Scott Sparrell-Building permit is still under review. No inspections till building permit is issued.
|