Final | 12/27/2018 | 12/28/2018 | 12/28/2018 | A | PASS |
Matt Wrobel
|
|
|
RUSSELL IS THE CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
PLM-Aging Inspection | 12/25/2018 | 12/25/2018 | 12/27/2018 | | PART |
Matt Wrobel
|
|
|
per dan ediger new line for lift station needs permitted this permit needs finaled out
|
PLM-Aging Inspection | 9/25/2018 | 9/25/2018 | 9/25/2018 | | NR |
Dan Ediger
|
|
|
wip
|
Plumbing Rough-in | 6/18/2018 | 6/19/2018 | 6/18/2018 | A | CANC |
Dan Ediger
|
|
|
JOB CONTACT - DAVID ###-#### Phone #: ###-#### >> Inspection requested via web by BECCA DUMMER Inspection cancelled from web by: BECCA DUMMER
|
Plumbing Rough-in | 6/15/2018 | 6/18/2018 | 6/18/2018 | A | PART |
Bill VanDegrift
|
|
|
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER this is for the single story sonth section. water main test and most of the drops in the walls, missing a sink or two that needs framing. waste and vent test east section ok. there will be other dwv sections on the south side. verify the approved plans are on site, they were not today.
|
Groundwork | 5/2/2018 | 5/3/2018 | 5/3/2018 | A | FAIL |
Dan Ediger
|
|
|
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. A fixture fitting cannot be laid in the horizontal. Two wye branch fittings must be used.
|
Groundwork | 4/30/2018 | 5/1/2018 | 5/1/2018 | A | PASS |
Dan Ediger
|
|
|
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Groundwork rooms 159, 160 and 163 floor drains.
|
Groundwork | 4/26/2018 | 4/27/2018 | 4/27/2018 | A | PASS |
Dan Ediger
|
|
|
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. East office drains and water service 100psi test. WS is copper and will be sleeved.
|
Groundwork | 4/25/2018 | 4/25/2018 | 4/25/2018 | P | CANC |
Dan Ediger
|
|
|
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Garage floor drains ok
|
Groundwork | 3/12/2018 | 3/13/2018 | 3/12/2018 | A | PASS |
Dan Ediger
|
|
|
DAVIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Completes hair trap line, North end building
|
Groundwork | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | PART |
Dan Ediger
|
|
|
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER.hair trap shelter
|
Groundwork | 2/13/2018 | 2/14/2018 | 2/14/2018 | A | PART |
Dan Ediger
|
|
|
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Parthial West ground work.
|
Groundwork | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PART |
Bill VanDegrift
|
|
|
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER deep waste mains center section tests ok
|
Groundwork | 2/1/2018 | 2/1/2018 | 2/1/2018 | P | PASS |
Dan Ediger
|
|
|
|
Groundwork | 1/31/2018 | 2/1/2018 | 2/1/2018 | A | FAIL |
Dan Ediger
|
|
|
DAVID IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. 1. Back to back fixtures above 2" must be served by a fixture fitting. 2. Provide full size cleanouts. 3. Trap arms exceeding max lengths. 4. Horizontal vents must be taken off the invert
|