Final | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen
|
Final | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | FAIL |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen. Pay reinspection fee prior to final
|
Final | 8/14/2018 | 8/15/2018 | 8/15/2018 | P | FAIL |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen. The garage floor cleanouts must be flush with the floor and glued to the pipe. Reinspection fee applied.
|
Plumbing Rough-in | 5/8/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen
|
Plumbing Rough-in | 4/27/2018 | 4/30/2018 | 4/30/2018 | P | CANC |
Dan Ediger
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Johansen Inspection cancelled from web by: Brian Johansen
|
Groundwork | 2/2/2018 | 2/5/2018 | 2/5/2018 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen
|