Other | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | PASS |
Dan Ediger
|
|
|
This permit was expired for lack of work after 180 days. The homeowner stated the contractor did not return after rough-in and work was completed under plm18-05334.
|
Final | 1/25/2019 | 1/25/2019 | 1/25/2019 | A | CANC |
Dan Ediger
|
|
|
|
DOC - Permit Expired | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | PASS |
Dan Ediger
|
|
|
This permit has had not action for more than 180days. A new permit was pulled, plm18-05334. The work was completed under this permit and finaled. The homeowner states the contractor under this permit did not return after the rough-in.
|
PLM-Aging Inspection | 12/12/2018 | 12/12/2018 | 12/12/2018 | | PASS |
Daryl Spivey
|
|
|
wip
|
Plumbing Rough-in | 2/14/2018 | 2/15/2018 | 2/15/2018 | P | PASS |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by Raul Castanon
|