Final | 9/10/2018 | 9/11/2018 | 9/11/2018 | A | PASS |
Daryl Spivey
|
|
|
Talked to eric about running t and p to washer box said leave a air gap
Keys are under top red paver on front porch Phone #: ###-#### Inspection requested via web by Mark Kelso
|
Plumbing Rough-in | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Bill VanDegrift
|
|
|
Calling back correction notice issue fixed Phone #: ###-#### Inspection requested via web by Mark Kelso ri ok
|
Plumbing Rough-in | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | FAIL |
Dan Ediger
|
|
|
Walked with Eric when he was ot talk with him on cleanouts was good with all the cleanouts in basement only since owner of building owns all units guage ln upstairs kitchen drain and upstairs lav drain. Water live pressure Phone #: ###-#### Inspection requested via web by Mark Kelso. Both units require a water softener rought-in with hard water run to the kitchen sink.
|
Water and/or Sewer | 7/9/2018 | 7/10/2018 | 7/10/2018 | A | PASS |
Dan Ediger
|
|
|
Eric came out and looked to approve bury except connections. Meters are live Phone #: ###-#### Inspection requested via web by Mark Kelso
|
Water and/or Sewer | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | PART |
Eric Strole
|
|
|
2 water main tests same trench Phone #: ###-#### Inspection requested via web by Mark Kelso-OK to cover waterlines except connections. Need to add waterlines to permit.
|
Groundwork | 5/31/2018 | 5/31/2018 | 5/31/2018 | P | PASS |
Dan Ediger
|
|
|
Mark Phone #: ###-####
|
Groundwork | 5/11/2018 | 5/11/2018 | 5/11/2018 | P | FAIL |
Dan Ediger
|
|
|
In basement Phone #: ###-#### Inspection requested via web by Mark Kelso. Provide a backwater valve for all of the fixtures in the basement, below the uppermost manhole.
|