Final | 9/19/2018 | 9/19/2018 | 9/19/2018 | P | PASS |
Eric Strole
|
|
|
|
Card not on site to sign | 9/19/2018 | 9/19/2018 | 9/19/2018 | P | PASS |
Eric Strole
|
|
|
|
Final | 9/18/2018 | 9/18/2018 | 9/18/2018 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Raul Castanon-Temp final ok, will final when permit for sprinklers is issued.
|
Final | 9/12/2018 | 9/13/2018 | 9/13/2018 | A | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Raul Castanon-Need expantion tank, airgap on t&P and hook up dog wash sink.
|
Plumbing Rough-in | 7/25/2018 | 7/25/2018 | 7/25/2018 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Raul Castanon
|
Plumbing Rough-in | 7/24/2018 | 7/25/2018 | 7/25/2018 | A | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Raul Castanon-Corrections not complete.
|
Plumbing Rough-in | 7/23/2018 | 7/24/2018 | 7/24/2018 | A | FAIL |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Raul Castanon--Need to equal cross sectional venting. Need to fix back graded vent & uncover waterlines.
|
Plumbing Rough-in | 7/19/2018 | 7/19/2018 | 7/19/2018 | P | PEND |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Raul Castanon-Waiting on engineer to address concerns on water service.
|
Water and/or Sewer | 7/5/2018 | 7/5/2018 | 7/5/2018 | P | PART |
Eric Strole
|
|
|
New waterline Phone #: ###-#### Inspection requested via web by Raul Castanon-Ok to cover inside only.
|
Groundwork | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PART |
Eric Strole
|
|
|
corrections made Phone #: ###-#### Inspection requested via web by Raul Castanon-Ground work pass. Still need new water service.
|
Groundwork | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PART |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Raul Castanon-Need to change 2" drain for rp to 3".
|